A TRUE COPY <br />CERTIFICATION ON LAST PAGE <br />RYAN L. BUTLER, CLERK <br />ATTACHMENT 3 <br />GRANT WORK PLAN <br />PROJECT TITLE: Indian River County Ixora Park Sewer Rehabilitation <br />PROJECT LOCATION: The Project will be located in the City of Vero Beach South within Indian River <br />County; Lat/Long (27.5999, -80.4059). <br />PROJECT BACKGROUND: Frequent failures of the Indian River County Ixora Park sanitary sewer <br />system result in sink holes in the community's roadways, presenting a public safety hazard and service <br />interruptions. This sewer system is adjacent to the county's South Relief Canal, a Tributary of the Indian <br />River Lagoon (IRL). The Ixora Park neighborhood is currently connected to the County sewer system <br />through delivery methods that are of a deficient nature creating potential impacts to the IRL. This Project <br />will consist of phasing out users connected to the sewer system with deficient connections and reconnecting <br />those residents back to the rehabilitated system, thereby protecting the IRL from inadvertent impacts. <br />PROJECT DESCRIPTION: Indian River County (Grantee) will rehabilitate and replace the sanitary <br />sewer collection system within the Ixora Park neighborhood (approximately 9,700 linear feet (LF) of <br />vitrified clay pipe) that has reached the end of its service life. The Grantee will relocate the water mains <br />and meter boxes from the back of parcels to the Right of Way line, along the front of the property lines, <br />making the utility easier to maintain and repair. <br />The Grantee does not anticipate that the funding under this Agreement will result in a fully completed <br />project, so this Agreement will cover a portion of the work. <br />TASKS: All documentation should be submitted electronically unless otherwise indicated. <br />Task 1: Design and Permitting <br />Deliverables: The Grantee will complete the design and obtain all necessary permits for construction of <br />the Indian River County Ixora Park Sewer Rehabilitation Project. <br />Documentation: The Grantee will submit: 1) a signed acceptance of the completed work to date, as <br />provided in the Grantee's Certification of Payment Request; and 2) a summary of design activities to date, <br />indicating the percentage of design completion for the time period covered in the payment request. For the <br />final documentation, the Grantee will also submit a copy of the design completed with the funding provided <br />for this task and a list of all required permits identifying issue dates and issuing authorities. <br />Performance Standard: The Department's Grant Manager will review the documentation to verify that <br />the deliverables have been completed as described above. Upon review and written acceptance by the <br />Department's Grant Manager, the Grantee may proceed with payment request submittal. <br />Payment Request Schedule: The Grantee may submit a payment request for cost reimbursement no more <br />frequently than monthly. <br />Task 2 : Bidding and Contractor Selection <br />Deliverables: The Grantee will prepare a bid package, publish a public notice, solicit bids, conduct pre-bid <br />meetings, and respond to bid questions in accordance with the Grantee's procurement process, to select one <br />or more qualified and licensed contractors to complete construction of the Ixora Park Sewer Rehabilitation. <br />DEP Agreement No. LPA0306, Attachment 3, Page 1 of 3 <br />