ARTICLE 12 - CHANGE OF CONTRACT PRICE; <br />CHANGE OF CONTRACT TIMES <br />12.01 Change of Contract Price <br />A. The Contract Price may only be changed by a <br />Change Order or by a Written Amendment. Any <br />Claim for an adjustment in the Contract Price shall be <br />based on written notice submitted by the party making <br />the Claim to the ENGINEER and the other party to the <br />Contract in accordance with the provisions of para- <br />graph 10.05. <br />B. The value of any Work covered by a Change <br />Order or of any Claim for an adjustment in the <br />Contract Price will be determined as follows: <br />1. where the Work involved is covered <br />by unit prices contained in the Contract <br />Documents, by application of such unit prices to <br />the quantities of the items involved (subject to <br />the provisions of paragraph 11.03 ); or <br />2. where the Work involved is not cov- <br />ered by unit prices contained in the Contract <br />Documents, by a mutually agreed lump sum <br />(which may include an allowance for overhead <br />and profit not necessarily in accordance with <br />paragraph 12.01.C.2); or <br />3. where the Work involved is not cov- <br />ered by unit prices contained in the Contract <br />Documents and agreement to a lump sum is <br />not reached under paragraph 12.01.6.2, on the <br />basis of the Cost of the Work (determined as <br />provided in paragraph 11.01) plus a <br />CONTRACTOR's fee for overhead and profit <br />(determined as provided in paragraph 12.01.C). <br />C. CONTRACTOR's Fee: The <br />CONTRACTOR's fee for overhead and profit shall be <br />determined as follows: <br />1. a mutually acceptable fixed fee; or <br />2. if a fixed fee is not agreed upon, then <br />a fee based on the following percentages of the <br />various portions of the Cost of the Work: <br />a. for costs incurred under para- <br />graphs 11.01.A.1 and 11.01.A.2, the <br />CONTRACTOR's fee shall be 15 percent; <br />b. for costs incurred under paragraph <br />11.01.A.3, the CONTRACTOR's fee shall <br />be five percent; <br />c. where one or more tiers of subcon- <br />tracts are on the basis of Cost of the Work <br />plus a fee and no fixed fee is agreed upon, <br />the intent of paragraph 12.01.C.2.a is that <br />the Subcontractor who actually performs <br />the Work, at whatever tier, will be paid a fee <br />of 15 percent of the costs incurred by such <br />Subcontractor under paragraphs 11.01.A.1 <br />and 11.01.A.2 and that any higher tier <br />Subcontractor and CONTRACTOR will <br />each be paid a fee of five percent of the <br />amount paid to the next lower tier Subcon- <br />tractor; <br />d. no fee shall be payable on the <br />basis of costs itemized under paragraphs <br />11.01.A.4, 11.01.A.5, and 11.01.6; <br />e. the amount of credit to be allowed <br />by CONTRACTOR to OWNER for any <br />change which results in a net decrease in <br />cost will be the amount of the actual net <br />decrease in cost plus a deduction in <br />CONTRACTOR's fee by an amount equal <br />to five percent of such net decrease; and <br />f. when both additions and credits are <br />involved in any one change, the adjustment <br />in CONTRACTOR's fee shall be computed <br />on the basis of the net change in <br />accordance with paragraphs 12.01.C.2.a <br />through 12.01.C.2.e, inclusive. <br />12.02 Change of Contract Times <br />A. The Contract Times (or Milestones) may only <br />be changed by a Change Order or by a Written <br />Amendment. Any Claim for an adjustment in the <br />Contract Times (or Milestones) shall be based on <br />written notice submitted by the party making the claim <br />to the ENGINEER and the other party to the Contract <br />in accordance with the provisions of paragraph 10.05. <br />B. Any adjustment of the Contract Times (or <br />Milestones) covered by a Change Order or of any <br />Claim for an adjustment in the Contract Times (or <br />Milestones) will be determined in accordance with the <br />provisions of this Article 12. <br />12.03 Delays Beyond CONTRACTOR's Control <br />A. Where CONTRACTOR is prevented from <br />completing any part of the Work within the Contract <br />Times (or Milestones) due to delay beyond the control <br />of CONTRACTOR, the Contract Times (or <br />Milestones) will be extended in an amount equal to the <br />time lost due to such delay if a Claim is made therefor <br />as provided in paragraph 12.02.A. Delays beyond the <br />control of CONTRACTOR shall include, but not be <br />limited to, acts or neglect by OWNER, acts or neglect <br />00700 - General Conditions REV 5-10-13 <br />00700 - 33 <br />F:\Public Works\ENGINEERING DIVISION PROJECTS\1506-Gifford Neighborhood 45th St BeautificationWdmin\bid documents Master Contract Documents\00700 - General Conditions <br />REV 5-10-13.doc <br />