Laserfiche WebLink
2. Remove all equipment and material from project site. <br />3. Perform contract closeout procedures. <br />3.02 Completion of all tasks outlined above (i.e., Subparagraphs a, b, and c) constitute <br />Final Completion. <br />3.03 Liquidated Damages <br />CONTRACTOR and OWNER recognize that time is of the essence of this Agreement and <br />that OWNER will suffer financial loss if the Work is not completed within the times specified <br />in paragraph 3.01 above, plus any extensions thereof allowed in writing as a change order <br />to this Agreement. The parties also recognize the delays, expense, and difficulties involved <br />in proving in a legal proceeding the actual loss suffered by OWNER if the Work is not <br />completed on time. Accordingly, instead of requiring any such proof, OWNER and <br />CONTRACTOR agree that as liquidated damages for delay (but not as a penalty), <br />CONTRACTOR shall pay OWNER $450.00 for each calendar day that expires after the time <br />specified in paragraph 3.01 for completion and readiness for final payment until the Work is <br />completed and ready for final payment. <br />ARTICLE 4 - CONTRACT PRICE <br />4.01 OWNER shall pay CONTRACTOR for completion of the Work ah amount in current funds <br />equal to the sum of the amounts determined pursuant to paragraph 4.01.A and summarized in <br />paragraph 4.01.B, below: <br />A. For all Work, at the prices stated in CONTRACTOR's Bid, attached hereto as an exhibit. <br />B. THE CONTRACT SUM subject to additions and deductions provided in the Contract <br />Documents: <br />Numerical Amount: $ 123,779.36 <br />Written Amount: One hundred twenty three thousand, seven hundred and seventy <br />nine dollars and thirty six cents <br />ARTICLE 5 - COMPENSATION <br />CONTRACTOR shall submit Applications for Payment on a monthly basis. Applications for <br />Payment will be processed by ENGINEER as provided in the Contract Documents. <br />5.1 Progress Payments. The OWNER shall make progress payments to the CONTRACTOR on <br />the basis of the approved partial payment request as recommended by ENGINEER in <br />accordance with the provisions of the Local Government Prompt Payment Act, Florida <br />Statutes section 218.70 ET. seq. The OWNER shall retain ten percent (10%) of the payment <br />amounts due to the CONTRACTOR until fifty percent (50%) completion of the work. After <br />fifty percent (50%) completion of the work is attained as certified to OWNER by ENGINEER <br />in writing, OWNER shall retain five percent (5%) of the payment amount due to <br />CONTRACTOR until final completion and acceptance of all work to be performed by <br />Section 00530-3 <br />