ADDENDUM #1 <br />1. Shape the surface of shoulders to within 0.1 foot of the plan cross-section. <br />2. Shape the earthwork to match adjacent pavement, curb, sidewalk, structures, <br />etc <br />3. Shape the bottom of ditches so that the ditch impounds no water. <br />4 When the work does not include construction of base or pavement, shape the <br />entire roadbed (shoulder point to shoulder point) to within 0.1 foot above or below the plan <br />cross-section <br />Ensure that the shoulder lines do not vary horizontally more than 0.3 foot from <br />the true lines shown in the plans <br />120-11.2 Operations Adjacent to Pavement: Carefully dress areas adjacent to <br />pavement areas to avoid damage to such pavement. Complete grassing of shoulder areas <br />prior to placing the final wearing course. Do not manipulate any embankment material on a <br />pavement surface. <br />When shoulder dressing is underway adjacent to a pavement lane being used to <br />maintain traffic, exercise extreme care to avoid interference with the safe movement of traffic. <br />120-12 Method of Measurement. <br />120-12.1 Excavation: Excavation will be paid for by volume, in cubic yards, calculated <br />by the method of average end areas, unless the Engineer determines that another method of <br />calculation will provide a more accurate result. The material will be measured in its original <br />position by field survey or by photogrammetric means as designated by the Engineer. <br />Measurement for payment will include the excavation of unsuitable material, lateral ditch <br />excavation, channel excavation, and excavation for structures and pipe. Payment will not be <br />made for excavation or embankment beyond the limits shown in the plans or authorized by <br />the Engineer. <br />120-12.2 Embankment: Measurement will be made on a loose volume basis, as <br />measured in trucks or other hauling equipment at the point of dumping on the road. Payment <br />will not be made for embankment beyond the limits shown in the plans or authorized by the <br />Engineer. <br />120-13 Basis of Payment. <br />120-13.1 General: Prices and payments for the work items included in this Section will <br />be full compensation for all work described herein, including excavating, dredging, hauling, <br />placing, and compacting; dressing the surface of the earthwork, and maintaining and <br />protecting the complete earthwork. <br />120-13.2 Excavation: The total quantity of all excavation specified under this Section <br />will be paid for at the Contract unit price for Excavation No payment will be made for the <br />excavation of any materials which are used for purposes other than those shown in the plans <br />or designated by the Engineer No payment will be made for materials excavated outside the <br />lines and grades given by the Engineer, unless specifically authorized by the Engineer. <br />120-13.3 Embankment. The total quantity of embankment specified in this Section will <br />be paid for at the Contract unit price for embankment. No payment will be made for materials <br />which are used for purposes other than those shown in the plans or designated by the <br />Engineer. No payment will be made for materials placed outside the lines and grades given by <br />the Engineer <br />01025-33 Technical Specifications <br />FlPublic Works\ENGINEERING DIVISION PROJECTS\1205-Vero Lake Estates Swk-87th St_101st Ave to CR510 <br />(LAP)1Admim\ADDENDUMS\ADDENDUM 1 \Technical Specifications Addendum #1 doc <br />