The sidewalks referenced above are under constriction- The attached Change Order No. 1 is to <br />increase the contract time by 25 days. The reason for the changes are as follows: Twenty one days <br />are for the delay in Florida Power & Light relocating three power poles on Old Winter Beach Road <br />and four days are being added for rain delays since the contract began on September 4, 2001. <br />The original scheduled project completion is January 1, 2002. The proposed date will become <br />January 26, 2002. <br />The contract amount of $531,191.95 will not be altered with this Change Order. <br />Alternative No. 1 - Approve Change Order No. 1 to increase the contract time by 25 days. <br />Alternative No. 2 - The Board could decide not to approve Change Order No. 1. <br />Staff recommends the board approve Alternative No. 1 to approve Change Order No. I to increase <br />the contract time by 25 days. <br />ON MOTION by Commissioner Adams, <br />SECONDED by Commissioner Stanbridge, the <br />Board unanimously approved Change Order No. 1 <br />with Tim Rose Contracting, increasing the contract <br />time by 25 days, as recommended by staff. <br />CHANGE ORDER IS ON FILE IN THE <br />OFFICE OF THE CLERK TO THE BOARD <br />DECEMBER 18, 2001 <br />It I w Ira 114 U <br />—97— <br />} <br />1� <br />> <br />The sidewalks referenced above are under constriction- The attached Change Order No. 1 is to <br />increase the contract time by 25 days. The reason for the changes are as follows: Twenty one days <br />are for the delay in Florida Power & Light relocating three power poles on Old Winter Beach Road <br />and four days are being added for rain delays since the contract began on September 4, 2001. <br />The original scheduled project completion is January 1, 2002. The proposed date will become <br />January 26, 2002. <br />The contract amount of $531,191.95 will not be altered with this Change Order. <br />Alternative No. 1 - Approve Change Order No. 1 to increase the contract time by 25 days. <br />Alternative No. 2 - The Board could decide not to approve Change Order No. 1. <br />Staff recommends the board approve Alternative No. 1 to approve Change Order No. I to increase <br />the contract time by 25 days. <br />ON MOTION by Commissioner Adams, <br />SECONDED by Commissioner Stanbridge, the <br />Board unanimously approved Change Order No. 1 <br />with Tim Rose Contracting, increasing the contract <br />time by 25 days, as recommended by staff. <br />CHANGE ORDER IS ON FILE IN THE <br />OFFICE OF THE CLERK TO THE BOARD <br />DECEMBER 18, 2001 <br />It I w Ira 114 U <br />—97— <br />1� <br />►It <br />The sidewalks referenced above are under constriction- The attached Change Order No. 1 is to <br />increase the contract time by 25 days. The reason for the changes are as follows: Twenty one days <br />are for the delay in Florida Power & Light relocating three power poles on Old Winter Beach Road <br />and four days are being added for rain delays since the contract began on September 4, 2001. <br />The original scheduled project completion is January 1, 2002. The proposed date will become <br />January 26, 2002. <br />The contract amount of $531,191.95 will not be altered with this Change Order. <br />Alternative No. 1 - Approve Change Order No. 1 to increase the contract time by 25 days. <br />Alternative No. 2 - The Board could decide not to approve Change Order No. 1. <br />Staff recommends the board approve Alternative No. 1 to approve Change Order No. I to increase <br />the contract time by 25 days. <br />ON MOTION by Commissioner Adams, <br />SECONDED by Commissioner Stanbridge, the <br />Board unanimously approved Change Order No. 1 <br />with Tim Rose Contracting, increasing the contract <br />time by 25 days, as recommended by staff. <br />CHANGE ORDER IS ON FILE IN THE <br />OFFICE OF THE CLERK TO THE BOARD <br />DECEMBER 18, 2001 <br />It I w Ira 114 U <br />—97— <br />