ANALYSIS <br />On April 18, 2002 at 7:00 p.m., an informational meeting was held for the benefit of the property owners, in the <br />multi—purpose room at the Pelican Island Elementary School in Sebastian. <br />Within the Phase III -D & III -E project area, East & West of Laconia Street, between Clearmont Street & Capon <br />Terrace, and between Granduer & Gladiola Avenue's there are 1433 lots and approximately 602 homes, to benefit <br />from this project. Typical platted lot sizes are .25 acre, plus or minus. <br />More effective management of project construction, inspections, cash flows, and interaction with property owners is <br />being accomplished by having divided Phases II and 11I into smaller projects, possibly making the bid process more <br />competitive. The attached map displays the area to benefit from the assessment projects, as divided into parts A, B, <br />C, D & E, for Phase [II (Attachment 2) This project will provide potable water and fire protection to an area noted <br />for failing well systems. The City of Sebastian is waiting for the completion of the water line installation in order to <br />complete road & drainage improvements and comply with bonding requirements. <br />Engineering design has been completed by the staff of the Department of Utility Services for Phase III -D & III -E <br />and we are now ready to begin the assessment process associated with this project, as outlined herein. A summary <br />assessment roll for Phase III -D & II[ -E is attached (Attachment 4). The full assessment roll is on file in the <br />commission office. This project is to be paid through the assessment of property owners along the proposed water <br />line route. Financing will be from the assessment fund 473. If needed, inter -fund borrowing will be available from <br />the capacity fee fund 472. The estimated project cost and amount to be assessed for Phase's II1-D and III -E is <br />$3,166,394.30 (Attachment -3). The estimated cost per square foot is $0.217507 (rounded). The actual assessed <br />cost, as with any project will be determined based on actual competitive bid prices. <br />On April 1, 2002, a letter was sent to the City Manager, of the City of Sebastian, with a copy of a draft agenda item, <br />summary assessment roll and a map of the project area (Attachment 5). <br />RECOMMENDATION <br />The staff of the Department of Utility Services recommends that the Board of County Commissioners approve the <br />attached Resolution III, which affirms the preliminary assessment on the subject project. <br />Manager of Assessment Projects Dan Chastain briefly reviewed the project for the <br />Board. <br />MAY 7, 2002 <br />Project No. <br />Lots <br />Parcel LD. <br />Nos./ Homes <br />ALL <br />OF <br />PHASE <br />HI <br />Locations <br />IS SOUTH <br />OF <br />CR <br />512 <br />& <br />SOUTHWEST <br />OF <br />BARBER <br />STREET <br />III -A UW -97 -16 -DS <br />891 <br />786 <br />/ 384 <br />South of Caravan Terrace with Periwinkle Drive along , <br />the South & .& West <br />III -B UW -97 -17 -DS <br />530 <br />458 <br />/ 239 <br />East of Laconia St of Shakespeare St.. <br />Between Crystal Mist & Lanfair Ave's <br />III -C UW -97 -18 -DS <br />900 <br />822 <br />/ 414 <br />Between Laconia & Barber St's , between Bayfront <br />Terrace and Rolling Hills (Lansdowne) <br />III -D UW -97 -19 -DS <br />698 <br />639 <br />/ 279 <br />East of Laconia St., between Clearmont & Capon <br />Streets. <br />III -E UW -97 -20 -DS <br />735 <br />654 <br />/ 323 <br />West of Laconia St, between Granduer & Gladiola <br />Avenue's <br />Total <br />3,754 <br />3,359 /L639 <br />South of CR 512 and SW of Barber Street <br />Engineering design has been completed by the staff of the Department of Utility Services for Phase III -D & III -E <br />and we are now ready to begin the assessment process associated with this project, as outlined herein. A summary <br />assessment roll for Phase III -D & II[ -E is attached (Attachment 4). The full assessment roll is on file in the <br />commission office. This project is to be paid through the assessment of property owners along the proposed water <br />line route. Financing will be from the assessment fund 473. If needed, inter -fund borrowing will be available from <br />the capacity fee fund 472. The estimated project cost and amount to be assessed for Phase's II1-D and III -E is <br />$3,166,394.30 (Attachment -3). The estimated cost per square foot is $0.217507 (rounded). The actual assessed <br />cost, as with any project will be determined based on actual competitive bid prices. <br />On April 1, 2002, a letter was sent to the City Manager, of the City of Sebastian, with a copy of a draft agenda item, <br />summary assessment roll and a map of the project area (Attachment 5). <br />RECOMMENDATION <br />The staff of the Department of Utility Services recommends that the Board of County Commissioners approve the <br />attached Resolution III, which affirms the preliminary assessment on the subject project. <br />Manager of Assessment Projects Dan Chastain briefly reviewed the project for the <br />Board. <br />MAY 7, 2002 <br />