Laserfiche WebLink
SECTION 02504 <br /> TESTING AND DISINFECTING WATER MAINS <br /> 1 . FILLING AND FLUSHING NEW WATER MAINS <br /> A. Prior to filling any new water main, an isolation valve (either existing or new) <br /> shall be installed between the existing water main and any new extension of <br /> the water main. The isolation valve shall be provided with a locking <br /> mechanism by the Contractor, with the key provided to the Utility <br /> Department. The valve shall remain locked in the closed position at all times <br /> except during flushing as supervised by the Utility Department and Engineer. <br /> Prior to connection of the new main to the isolation valve, the valve shall be <br /> pressure tested to 150 psi and checked for watertightness . Any valve which is <br /> found not to be watertight shall be replaced at the Contractor's expense. <br /> B . Filling of the new water main shall be by means of a temporary fill connection <br /> utilizing either of the following : <br /> 1 ) A 2-inch jumper across the isolation valve from the existing active <br /> water main to the new water main. The jumper shall be connected : to the <br /> mains using previously specified 24nch by pipe diameter tapping <br /> saddles . The corporation stop shall be 2 -inch in size, manufactured as <br /> previously specified, except that the tapping end shall be M. I . P . T. and the <br /> fill connection end shall be F . I .P . T. The jumper shall incorporate an <br /> AWWA approved and certified backflow preventer mounted a <br /> minimum 184nches above ground surface and a gate valve for <br /> regulating flow. <br /> 2) A 24nch jumper from an active fire hydrant to the new water main . <br /> The jumper shall be connected to the new main as specified above . <br /> The jumper shall incorporate a hydrant meter, an AWWA approved and <br /> certified backflow preventer and a flow regulating gate valve . <br /> The fill connection shall be used for filling the new water main and for pulling <br /> bacteriological samples from the new main. The fill connection shall be <br /> maintained in place until after filling, flushing, testing, disinfection of the new <br /> water system, and clearance for use from the Florida Department of <br /> Environmental Protection (F . D .E . P . ) has been received. After testing , the fill <br /> connection shall remain open to provide a minimum 20 psi in the new water <br /> system until clearance for use from the Florida Department of <br /> Environmental Protection (F . D . E . P .) has been received . <br /> C . Flushing of the new water main system shall be conducted under very <br /> controlled conditions . The Contractor shall provide 3 /4 -inch by pipe <br /> C AD ow n l o ad\techspec-02 504 . doc <br />