does not involve a change in the Contract Price or the Contract 35. Project Manual--The bound documentary
<br /> Times . information prepared for bidding and constructing the Work. A
<br /> listing of the contents of the Project Manual , which may be
<br /> 22. General Requirements--Sections of Division 1 of bound in one or more volumes , is contained in the table(s ) of
<br /> the Specifications . The General Requirements pertain to all contents.
<br /> sections of the Specifications .
<br /> 36. Radioactive Material--Source, special nuclear, or
<br /> 23. Hazardous Environmental Condition--The byproduct material as defined by the Atomic Energy Act of 1954
<br /> presence at the Site of Asbestos , PCBs, Petroleum, Hazardous (42 USC Section 2011 et seq . ) as amended from time to time.
<br /> Waste, or Radioactive Material in such quantities or
<br /> circumstances that may present a substantial danger to persons 37. Resident Project Representative--The authorized
<br /> or property exposed thereto in connection with the Work. representative of ENGINEER who may be assigned to the Site
<br /> or any part thereof.
<br /> 24. Hazardous Waste—The term Hazardous Waste
<br /> shall have the meaning provided in Section 1004 of the Solid 38. Samples—Physical examples of materials ,
<br /> Waste Disposal Act (42 USC Section 6903 ) as amended from equipment, or workmanship that are representative of some
<br /> time to time. portion of the Work and which establish the standards by which
<br /> such portion of the Work will be judged .
<br /> 25. Laws and Regulations; Laws or Regulations—Any
<br /> and all applicable laws , rules , regulations, ordinances, codes, 39. Shop Drawings—All drawings , diagrams, illustra-
<br /> and orders of any and all governmental bodies, agencies , tions , schedules , and other data or
<br /> information which are
<br /> authorities, and courts having jurisdiction . specifically prepared or assembled by or for CONTRACTOR
<br /> and submitted by CONTRACTOR to illustrate some portion of
<br /> 26. Liens—Charges , security interests, or the Work.
<br /> encumbrances upon Project funds , real property, or personal
<br /> property. 40. Site—Lands or areas indicated in the Contract
<br /> Documents as being furnished by OWNER upon which the
<br /> 27. Milestone—A principal event specified in the Work is to be performed, including rights-of-way and
<br /> easements
<br /> Contract Documents relating to an intermediate completion date for access thereto, and such other lands furnished by OWNER
<br /> or time prior to Substantial Completion of all the Work. which are designated for the use of CONTRACTOR.
<br /> 28. Notice of Award—The written notice by OWNER 41 . Specifications--That part of the Contract
<br /> to the apparent successful bidder stating that upon timely Documents consisting of written technical
<br /> descriptions of
<br /> compliance by the apparent successful bidder with the materials, equipment, systems , standards, and workmanship as
<br /> conditions precedent listed therein, OWNER will sign and applied to the Work and certain administrative details applicable
<br /> deliver the Agreement. thereto.
<br /> 29. Notice to Proceed--A written notice given by 42. Subcontractor--An individual or entity having
<br /> a
<br /> OWNER to CONTRACTOR fixing the date on which the Con- direct contract with CONTRACTOR or with any other
<br /> tract Times will commence to run and on which CONTRACTOR Subcontractor for the performance of a part of the Work at the
<br /> shall start to perform the Work under the Contract Documents . Site.
<br /> 30. OWNER--The individual , entity, public body, or 43. Substantial Completion--The time at which the
<br /> authority with whom CONTRACTOR has entered into the Work (or a specified part thereofl has progressed to
<br />the point
<br /> Agreement and for whom the Work is to be performed. where, in the opinion of ENGINEER, the Work (or a specified
<br /> part thereof) is sufficiently complete, in accordance with the
<br /> 31 . Partial Utilization--Use by OWNER of a substan- Contract Documents , so that the Work (or a specified
<br /> part
<br /> tially completed part of the Work for the purpose for which it is thereof) can be utilized for the purposes for which it is
<br /> intended.
<br /> intended (or a related purpose) prior to Substantial Completion The terms "substantially complete" and "substantially com-
<br /> of all the Work. pleted" as applied to all or part of the Work refer to Substantial
<br /> Completion thereof.
<br /> 32. PCBs—Polychlorinated biphenyls .
<br /> 44 . Supplementary Conditions--That part of the
<br /> 33. Petroleum—Petroleum , including crude oil or any Contract Documents which amends or supplements these
<br /> fraction thereof which is liquid at standard conditions of General Conditions.
<br /> temperature and pressure (60 degrees Fahrenheit and 14. 7
<br /> pounds per square inch absolute), such as oil , petroleum, fuel 45. Supplier--A manufacturer, fabricator, supplier,
<br /> oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with distributor, materialman , or vendor having a direct
<br /> contract with
<br /> other non-Hazardous Waste and crude oils . CONTRACTOR or with any Subcontractor to furnish materials
<br /> or equipment to be incorporated in the Work by CONTRACTOR
<br /> 34. Project—The total construction of which the Work or any Subcontractor.
<br /> to be performed under the Contract Documents may be the
<br /> whole, or a part as may be indicated elsewhere in the Contract 46. Underground Facilities--All underground
<br /> Documents. pipelines, conduits , ducts , cables , wires , manholes , vaults ,
<br /> tanks , tunnels , or other such facilities or attachments , and any
<br /> encasements containing such facilities, including those that
<br /> 00700 - 6
<br />
|