4. Utility Subsurface Locates — Locate sketches of each subsurface utility identified . <br /> SECTION IV — TIME FOR COMPLETION <br /> A. Submittal Dates <br /> The FDOT is scheduled to submit Right of Way maps in December 2006 requiring the 60% <br /> and 90% submittal dates to change. <br /> The 60% Design Drawing Submittal Date is moved three months to February 28, 2007 per <br /> letter dated October 26, 2006 from the County. The 90% Design Drawing Submittal Date is <br /> moved two months to July 30, 2007. <br /> CR 510 Amendment 1 Page 3 of 5 10/26/06 <br />