programs, or safety practices, nor shall the Consultant have any authority or responsibility to stop or
<br /> direct the work of any contractor.
<br /> While it is not anticipated that there will be hazardous materials or conditions encountered on this project,
<br /> should any such conditions be discovered during this scope of services, the Consultant shall notify IRCU
<br /> of hazardous substances or conditions not contemplated in this Scope of services of which the Consultant
<br /> actually becomes aware . Upon such notice by the Consultant, the Consultant may stop affected portions
<br /> of its services until the hazardous substance or condition is eliminated. The parties shall decide if the
<br /> Consultant is to proceed with the services and if the Consultant is to conduct testing and evaluations, and
<br /> the parties may enter into further agreements as to the additional scope, fee, and terms for such services .
<br /> ASSUMPTIONS and Additional Services
<br /> L It is assumed that ground-water, sediment quality, and surface water quality data monitoring in the
<br /> project area will not be necessary and is not provided under this scope.
<br /> 2 . Surveying and bathymetry outside of existing available data and beyond the scope listed herein can be
<br /> provided, as additional services .
<br /> 3 . Monitoring beyond what is listed herein and as defined by the DEP during the ERP process.
<br /> 4. Environmental Resource Permitting services in vicinity of Marsh Island, if necessary.
<br /> SCHEDULE
<br /> The scope described herein is anticipated to take approximately ten to fourteen months from notice to
<br /> proceed. Kimley-Horn will work diligently to have the permitting scope complete within two months,
<br /> and bid the project concurrently with the permitting process in order for construction to commence prior
<br /> to hurricane season. However, permitting agency review, bidding, and contractor delays are beyond our
<br /> control and make take longer than anticipated.
<br /> Permitting and bidding: 2 - 4 months
<br /> Construction: 10 - 12 months
<br /> Total t2 - 16 months
<br /> FEES
<br /> Consultant will provide these services in accordance with our non-exclusive professional Consulting
<br /> Agreement dated April 6, 2004 . Consultant will provide these Services as described herein on a lump
<br /> sum basis as follows :
<br /> Amount
<br /> Task Original Amendment ammoved Amendment Revised
<br /> No. Task Amount #1 Chane to date #2 ChaneAmount
<br /> 1 Meetings $ 17,790 $0 $ 17,790 $0 $ 17,790
<br /> 2 Collection of Existing Data $ 10,330 $0 $ 10,330 $0 $ 10,330
<br /> 3 Field Survey and Data Collection $24,000 $225500 $461500 $53500 $52,000
<br /> 4 Design $2200 $ 12,400 $35,200 $ 13,600 $483800
<br /> 5 Environmental Resources Permitting $49,500 $0 $49,500 $0 $49,500
<br /> 6 Permitting and Agency Coordination $ 19,800 $4,400 $24,200 $0 $24,200
<br /> 7 Construction Permitting (DEP) $75550 $3,400 $ 10,950 $6,000 $ 16,950
<br /> 8 Construction Phase Services $63,230 $ 10,800 $74,030 $ 14,300 $885330
<br /> TOTAL = $215,000 $53,500 $268,500 $39,400 $307,900
<br /> H904457200'TScope�Wabasso HDD Proposal-Amendment 2 revldoc
<br /> 3 of 3