Laserfiche WebLink
SECTION 01201 <br /> PRE -CONSTRUCTION CONFERENCE <br /> PART1 -- GENERAL <br /> 1 .01 REQUIREMENTS INCLUDED <br /> A. Engineer shall schedule and administer the preconstruction conference <br /> and shall perform the following duties : <br /> 1 . Prepare agenda for meeting . <br /> 2 . Give notice of meeting three days in advance of meeting date . <br /> 3 . Make physical arrangements for meeting . <br /> 4 . Preside at meeting . <br /> 5 . Record the minutes , which shall include all significant proceedings <br /> and decisions . <br /> 6 . Reproduce and distribute copies of minutes within fifteen ( 15 ) working <br /> days after meeting . Minutes shall be distributed to all participants in <br /> the meeting and to all parties affected by decisions made at the <br /> meeting . <br /> 1 .02 RELATED REQUIREMENTS <br /> A. Section 01000 : Summary of Work. <br /> B . Section 01311 : Construction Schedule . <br /> C . Section 01340 : Shop Drawings, Product Data and Samples . <br /> D . Section 01720 : Project Record Documents . <br /> 1 .03 PRECONSTRUCTION CONFERENCE <br /> A. Engineer will schedule meeting with Contractor, Owner and other affected <br /> parties . <br /> B . Location of the preconstruction meeting : The project site or a nearby <br /> office to be selected by Owner/Engineer. <br /> C . Attendance: <br /> 1 . Owner/Owner's representative . <br /> 2 . Engineer/Engineer's representative and his professional <br /> consultant . <br /> 3 . Contractor/Contractor's superintendent. <br /> 4 . Local utilities representatives . <br /> 5 . Local government agencies representative . <br /> 01201 Preconstruction Conference.doc <br /> 01201 - 1 <br /> JW-029 12 inch WM - Vera Lake Es[ates\Documents\Rep h%Tidi ing Contract SpecificationM01201 Preconstmction Conference.doc <br />