does not involve a change in the Contract Price or the Contract
<br />Times.
<br />22. General Requirements—Sections of Division 1 of
<br />the Specifications. The General Requirements pertain to all
<br />sections of the Specifications.
<br />23. Hazardous Environmental Condition --The
<br />presence at the Site of Asbestos, PCBs, Petroleum, Hazardous
<br />Waste, or Radioactive Material in such quantities or
<br />circumstances that may present a substantial danger to persons
<br />or property exposed thereto in connection with the Work.
<br />24. Hazardous Waste --The term Hazardous Waste
<br />shall have the meaning provided in Section 1004 of the Solid
<br />Waste Disposal Act (42 USC Section 6903) as amended from
<br />time to time.
<br />25. Laws and Regulations; Laws or Regulations --
<br />Any and all applicable laws, rules, regulations, ordinances,
<br />codes, and orders of any and all governmental bodies,
<br />agencies, authorities, and courts having jurisdiction.
<br />26. Liens—Charges, security interests, or
<br />encumbrances upon Project funds, real property, or personal
<br />property.
<br />27. Milestone—A principal event specified in the
<br />Contract Documents relating to an intermediate completion date
<br />or time prior to Substantial Completion of all the Work.
<br />28. Notice of Award --The written notice by OWNER
<br />to the apparent successful bidder stating that upon timely
<br />compliance by the apparent successful bidder with the
<br />conditions precedent listed therein, OWNER will sign and
<br />deliver the Agreement.
<br />29. Notice to Proceed --A written notice given by
<br />OWNER to CONTRACTOR fixing the date on which the Con-
<br />tract Times will commence to run and on which CONTRACTOR
<br />shall start to perform the Work under the Contract Documents.
<br />30.
<br />OWNER --The individual,
<br />entity, public
<br />body, or
<br />authority with
<br />whom CONTRACTOR
<br />has entered
<br />into the
<br />Agreement and for whom the Work is to
<br />be performed.
<br />one or more
<br />31. Partial Utilization—Use by OWNER of a substan-
<br />tially completed part of the Work for the purpose for which it is
<br />intended (or a related purpose) prior to Substantial Completion
<br />of all the Work.
<br />32. PCBs—Polychlorinated biphenyls.
<br />33. Petroleum—Petroleum, including crude oil or any
<br />fraction thereof which is liquid at standard conditions of
<br />temperature and pressure (60 degrees Fahrenheit and 14.7
<br />pounds per square inch absolute), such as oil, petroleum, fuel
<br />oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with
<br />other non -Hazardous Waste and crude oils.
<br />34. Project --The total construction of which the Work
<br />to be performed under the Contract Documents may be the
<br />whole, or a part as may be indicated elsewhere in the Contract
<br />Documents.
<br />36. Radioactive Matenal—Source, special nuclear, or
<br />byproduct material as defined by the Atomic Energy Act of 1954
<br />(42 USC Section 2011 et seq.) as amended from time to time.
<br />37. Resident Project Representative --The authorized
<br />representative of ENGINEER who may be assigned to the Site
<br />or any part thereof.
<br />38. Samples --Physical examples of materials,
<br />equipment, or workmanship that are representative of some
<br />portion of the Work and which establish the standards by which
<br />such portion of the Work will be judged.
<br />39. Shop Drawings—All drawings, diagrams, illustra-
<br />tions, schedules, and other data or information which are
<br />specifically prepared or assembled by or for CONTRACTOR
<br />and submitted by CONTRACTOR to illustrate some portion of
<br />the Work.
<br />40. Site—Lands or areas indicated in the Contract
<br />Documents as being furnished by OWNER upon which the
<br />Work is to be performed, including rights-of-way and easements
<br />for access thereto, and such other lands furnished by OWNER
<br />which are designated for the use of CONTRACTOR.
<br />41. Specifications --That part of the Contract
<br />Documents consisting of written technical descriptions of
<br />materials, equipment, systems, standards, and workmanship as
<br />applied to the Work and certain administrative details applicable
<br />thereto.
<br />42. Subcontractor --An individual or entity having a
<br />direct contract with CONTRACTOR or with any other
<br />Subcontractor for the performance of a part of the Work at the
<br />Site.
<br />43. Substantial Completion --The time at which the
<br />Work (or a specified part thereof) has progressed to the point
<br />where, in the opinion of ENGINEER, the Work (or a specified
<br />part thereof) is sufficiently complete, in accordance with the
<br />Contract Documents, so that the Work (or a specified part
<br />thereof) can be utilized for the purposes for which it is intended.
<br />The terms "substantially complete" and `substantially com-
<br />pleted" as applied to all or part of the Work refer to Substantial
<br />Completion thereof.
<br />44. Supplementary Conditions --That part of the
<br />Contract Documents which amends or supplements these
<br />General Conditions.
<br />45. Supplier—A manufacturer, fabricator, supplier,
<br />distributor, materialman, or vendor having a direct contract with
<br />CONTRACTOR or with any Subcontractor to furnish materials
<br />or equipment to be incorporated in the Work by CONTRACTOR
<br />or any Subcontractor.
<br />46. Underground Facilities—All underground
<br />pipelines, conduits, ducts, cables, wires, manholes, vaults,
<br />tanks, tunnels, or other such facilities or attachments, and any
<br />encasements containing such facilities, including those that
<br />00700 General Conditions (EJCDC).doe
<br />00700-6
<br />JW7-02912 Inch WM- Vera Lake EstatesDmumentsWeponst sddintt Conuvc, SPeeikAnQ1ntl0o7W GCcCrd I Conditions I EJCDCydoc
<br />35. Project
<br />Manual --The bound
<br />documentary
<br />information prepared for bidding and constructing the Work. A
<br />listing of
<br />the contents
<br />of the Project Manual,
<br />which may be
<br />bound in
<br />one or more
<br />volumes, is contained in
<br />the table(s) of
<br />contents.
<br />36. Radioactive Matenal—Source, special nuclear, or
<br />byproduct material as defined by the Atomic Energy Act of 1954
<br />(42 USC Section 2011 et seq.) as amended from time to time.
<br />37. Resident Project Representative --The authorized
<br />representative of ENGINEER who may be assigned to the Site
<br />or any part thereof.
<br />38. Samples --Physical examples of materials,
<br />equipment, or workmanship that are representative of some
<br />portion of the Work and which establish the standards by which
<br />such portion of the Work will be judged.
<br />39. Shop Drawings—All drawings, diagrams, illustra-
<br />tions, schedules, and other data or information which are
<br />specifically prepared or assembled by or for CONTRACTOR
<br />and submitted by CONTRACTOR to illustrate some portion of
<br />the Work.
<br />40. Site—Lands or areas indicated in the Contract
<br />Documents as being furnished by OWNER upon which the
<br />Work is to be performed, including rights-of-way and easements
<br />for access thereto, and such other lands furnished by OWNER
<br />which are designated for the use of CONTRACTOR.
<br />41. Specifications --That part of the Contract
<br />Documents consisting of written technical descriptions of
<br />materials, equipment, systems, standards, and workmanship as
<br />applied to the Work and certain administrative details applicable
<br />thereto.
<br />42. Subcontractor --An individual or entity having a
<br />direct contract with CONTRACTOR or with any other
<br />Subcontractor for the performance of a part of the Work at the
<br />Site.
<br />43. Substantial Completion --The time at which the
<br />Work (or a specified part thereof) has progressed to the point
<br />where, in the opinion of ENGINEER, the Work (or a specified
<br />part thereof) is sufficiently complete, in accordance with the
<br />Contract Documents, so that the Work (or a specified part
<br />thereof) can be utilized for the purposes for which it is intended.
<br />The terms "substantially complete" and `substantially com-
<br />pleted" as applied to all or part of the Work refer to Substantial
<br />Completion thereof.
<br />44. Supplementary Conditions --That part of the
<br />Contract Documents which amends or supplements these
<br />General Conditions.
<br />45. Supplier—A manufacturer, fabricator, supplier,
<br />distributor, materialman, or vendor having a direct contract with
<br />CONTRACTOR or with any Subcontractor to furnish materials
<br />or equipment to be incorporated in the Work by CONTRACTOR
<br />or any Subcontractor.
<br />46. Underground Facilities—All underground
<br />pipelines, conduits, ducts, cables, wires, manholes, vaults,
<br />tanks, tunnels, or other such facilities or attachments, and any
<br />encasements containing such facilities, including those that
<br />00700 General Conditions (EJCDC).doe
<br />00700-6