Laserfiche WebLink
EXHIBIT B <br /> SERVICES , COMPENSATION , AND TIME FOR COMPLETION <br /> This Work Order No . 1 is in accordance with the existing AGREEMENT dated August 22 , 2002 between <br /> LBFH, Inc . (Boyle Engineering Corp . ) (ENGINEER) and Indian River Community College ( IRCC ) . This <br /> Work Order No . 1 is issued to ENGINEER by Indian River County ( COUNTY ) piggy backing on the <br /> agreement between the ENGINEER and IRCC , amended as follows : <br /> SECTION I — PROJECT LIMITS <br /> This Work Order No . 1 is for the ENGINEER to perform an additional design related to the Indian River <br /> County/Indian River Community College- College Lane Extension and Bridge Replacement project located <br /> in Indian River County and lying in a portion of Sections 5 and 8 , Township 33 South , Range 39 East . <br /> SECTION II — SCOPE OF SERVICES <br /> As agreed upon between ENGINEER and COUNTY , ENGINEER shall provide Professional <br /> Engineering services to complete all tasks as outlined in this Work Order No . 1 described as follows : <br /> • Utility Design : <br /> 1 . Boyle will modify the existing construction plans for the College Lane Extension and <br /> Bridge Replacement project to include the extension of a 16- inch water main from a <br /> connection point at the existing 12- inch water main along the north side of the IRCC <br /> campus near the west end of the existing College Lane , terminating at the west end of the <br /> intersection of College Lane and 66`h Avenue . The water main will be located on the <br /> north side of the right-of- way , will cross the road east of the bridge and cross the <br /> IRFWCD Lateral A Canal on the south side of the bridge . The water main will be <br /> designed to meet Indian River County Department of Utility Services (IRCUSD) <br /> standards and FDEP requirements . <br /> 2 . This design assumes that there is 3 , 800 LF of 16- inch water main located at the back of <br /> the proposed sidewalk, with fire hydrants spaced at every 500-feet, sampling points at <br /> ever 1 ,200-feet and at dead ends, valves at every 1 ,500-feet, air relief valves at all high <br /> points , up to 5 conflicts with proposed utilities and 2 directional drills underneath the <br /> existing IRCC driveways . This design also assumes that there will be no aerial canal <br /> crossings or design of jack and bore installations, structural or retaining wall design , and <br /> conflicts with existing or proposed landscaping , or additional survey . These services , if <br /> required , will be provided upon addition l approvals from the COUNTY . <br /> 3 . Construction Drawings that are 90% complete will be used to make the FDEP submittal <br /> on behalf of the COUNTY . ENGINEER shall respond to as many as one ( 1 ) Request <br /> for Additional Information (RAI) from the FDEP . The COUNTY shall pay FDEP the <br /> permitting fees directly . <br /> 4 . ENGINEER shall prepare project specifications for the construction of the 16-inch water <br /> main for inclusion in the College Lane Extension and Bridge Replacement project <br /> specifications manual . It is assumed that these projects will be bid , awarded and <br /> constructed as a single-phased project. <br /> 5 . The permitted drawings will be incorporated into the 100% complete construction <br /> drawings for the College Lane Extension & Bridge Replacement project. <br /> 1 <br />