ARTICLE 3 CONTRACTOR
<br /> § 3. 1 GENERAL
<br /> § 3. 1 . 1 The Contractor is the person or entity identified as such in the Agreement and is referred to throughout the
<br /> Contract Documents as if singular in number. The term " Contractor" means the Contractor or the Contractor' s
<br /> authorized representative .
<br /> § 3.1 .2 The Contractor shall perform the Work in accordance with the Contract Documents.
<br /> § 3 . 1 .3 The Contractor shall not be relieved of its obligations to perform the Work in accordance with the Contract
<br /> Documents either by activities or duties of the Architect in the Architect ' s administration of the Contract, or by tests,
<br /> inspections or approvals required or performed by persons other than the Contractor.
<br /> § 3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR
<br /> § 3.2. 1 Since the Contract Documents are complementary, before starting each portion of the Work, the Contractor
<br /> shall carefully study and compare the various Drawings and other Contract Documents relative to that portion of the
<br /> Work, as well as the information furnished by the Owner pursuant to Section 2. 2. 3 , shall take field measurements of
<br /> any existing conditions related to that portion of the Work and shall observe any conditions at the site affecting it.
<br /> These obligations afe for- the purpose of f6eilitafing eenstfuetien by the Centfaeter- and afe not for- the purpose e
<br /> dissever-ing-Any errors, ewiissiew , inconsistencies or ineensisteneies omissions in the Contract Doeuments;
<br /> ho . . e . e., »:.; �. � , ...vv.isisteneies er effAssion&-Documents discovered by the Contractor shall be reported
<br /> promptly to the Architect and the Owner as a request for information in such form as the Architect or the Owner
<br /> may require .
<br /> § 3.2.2 Any design errors or omissions noted by the Contractor during this review shall be reported promptly to the
<br /> Arehiteet, Architect and the Owner in writing, but it is recognized that the Ce ' s ontractor' s review is made
<br /> in the r'oTContractor' s capacity as a contractor and not as a licensed design professional unless otherwise
<br /> specifically provided in the Contract Documents . The-While the Contractor is not required to ascertain that the
<br /> Contract Documents are in accordance with applicable laws , statutes, ordinances, building codes, and rules and
<br /> regulations, but any nonconformity discovered by or made known to the Contractor shall be reported promptly to the
<br /> Art-. Architect and the Owner in writing.
<br /> § 3.2.3 If the Contractor believes that additional cost or time is involved because of clarifications or instructions
<br /> issued by the Architect in response to the Contractor ' s notices or requests for information pursuant to Sections 3 . 2. 1
<br /> and 3 . 2. 2, the Contractor shall make Claims as provided in Sections 4 . 3 . 6 and 4. 3 .7 . If the Contractor fails to
<br /> perform the obligations of Sections 3 . 2. 1 and 3 . 2 .2, the Contractor shall pay such costs and damages to the Owner as
<br /> would have been avoided if the Contractor had performed such obligations . The Contractor shall not be liable to the
<br /> Owner or Architect for damages resulting from errors, inconsistencies or omissions in the Contract Documents or
<br /> for differences between field measurements or conditions and the Contract Documents unless the Contractor
<br /> recognized or, in the exercise of ordinary care, reasonably should have recognized such error, inconsistency,
<br /> omission or difference and knowingly failed to report it in writing to the Architect and the A ehitecrOwner.
<br /> § 3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
<br /> § 3.3. 1 The Contractor shall supervise and direct the Work, using the Contractor' s best skill and attention. The
<br /> Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences
<br /> and procedures and for coordinating all portions of the Work under the Gentfast orale.. .. the Genu-aet T,eetiments
<br /> giNze other- speeifie instfuetions eeneeming these matters. if the Gentfaet Doeuments give speeffie instr-uetiefis
<br /> jobsite safety ther-eef and, exeept as stated below, shall be fully and solely responsible fef the jobsite safety of sueh
<br /> ,
<br /> teehniques, sequenees of pfeeedtwes may nat be safe, the Gentr-aeter shall give timely written netiee to the Owne
<br /> and Afvhiteet and shall net pfeceed with that per-fien ef the Work %ritheut
<br /> Architect. if the GentraeteF is then instmeted to proceed with the requifed means, fnetheds , techniques , sequences o
<br /> pr-eeedur-es without aeeeptanee of ehanges proposed by the Centimeter-, the Owner- shall be solely responsible for- any
<br /> resulting less or- ontract.
<br /> § 3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor' s employees ,
<br /> Subcontractors and their agents and employees, and other persons or entities performing portions of the Work for or
<br /> on behalf of the Contractor or any of its Subcontractors.
<br /> AIA Document A201TM — 1997. Copyright ® 1911 , 1915, 1918, 1925, 1937, 1951 , 1958, 1961 , 1963, 1966, 1967, 1970, 1976, 1987 and 1997
<br /> by The
<br /> American Institute of Architects. All rights reserved. WARNING : This AIA® Document Is protected by U.S. Copyright Law and International Treaties.
<br /> 13
<br /> Unauthorized reproduction or distribution of this AIO Document, or any portion of It, may result In severe civil and criminal penalties, and will be
<br /> prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 17:14:54 on 05/25/2005 under Order
<br /> No. 1000126313_1 which expires on 6/29/2005, and is not for resale.
<br /> User Notes: (3418817618)
<br />
|