A. CONTRACTOR shall designate a qualified and
<br /> experienced safety representative at the Site whose duties and a. all field measurements , quantities , dimen-
<br /> responsibilities shall be the prevention of accidents and the sions , specified performance criteria , installation
<br /> maintaining and supervising of safety precautions and requirements , materials , catalog numbers , and
<br /> programs• similar information with respect thereto;
<br /> 6. 15 Hazard Communication Programs{tc In "6. 15 b. all materials with respect to intended use,
<br /> Hazard Communication Programs7 fabrication, shipping, handling , storage, assembly,
<br /> and installation pertaining to the performance of the
<br /> A. CONTRACTOR shall be responsible for coordinating Work;
<br /> any exchange of material safety data sheets or other hazard
<br /> communication information required to be made available to or c. all information relative to means, methods ,
<br /> exchanged between or among employers at the Site in techniques , sequences , and procedures of
<br /> accordance with Laws or Regulations , construction and safety precautions and programs
<br /> incident thereto; and
<br /> 6. 16 Emergencies{tc In "6. 16 Emergencies '
<br /> d. CONTRACTOR shall also have reviewed
<br /> A. In emergencies affecting the safety or protection of and coordinated each Shop Drawing or Sample with
<br /> persons or the Work or property at the Site or adjacent thereto, other Shop Drawings and Samples and with the
<br /> CONTRACTOR is obligated to act to prevent threatened dam- requirements of the Work and the Contract Docu-
<br /> age, injury, or loss. CONTRACTOR shall give ENGINEER ments .
<br /> prompt written notice if CONTRACTOR believes that any
<br /> significant changes in the Work or variations from the Contract 2. Each submittal shall bear a stamp or specific
<br /> Documents have been caused thereby or are required as a written indication that CONTRACTOR has satisfied
<br /> result thereof. If ENGINEER determines that a change in the CONTRACTOR's obligations under the Contract
<br /> Contract Documents is required because of the action taken by Documents with respect to CONTRACTOR's review
<br /> CONTRACTOR in response to such an emergency, a Work and approval of that submittal .
<br /> Change Directive or Change Order will be issued.
<br /> 3. At the time of each submittal, CONTRACTOR
<br /> 6. 17 Shop Drawings and Samples{tc In "6. 17 shall give ENGINEER specific written notice of such
<br /> Shop Drawings and Samples7 variations , If any, that the Shop Drawing or Sample
<br /> submitted may have from the requirements of the
<br /> A. CONTRACTOR shall submit Shop Drawings to Contract Documents , such notice to be in a written com-
<br /> ENGINEER for review and approval in accordance with the munication separate from the submittal; and, in addition,
<br /> acceptable schedule of Shop Drawings and Sample submittals. shall cause a specific notation to be made on each
<br /> All submittals will be identified as ENGINEER may require and Shop Drawing and Sample submitted to ENGINEER for
<br /> in the number of copies specified In the General Requirements, review and approval of each such variation.
<br /> The data shown on the Shop Drawings will be complete with
<br /> respect to quantities, dimensions , specified performance and E. ENGINEER's Review
<br /> design criteria, materials, and similar data to show ENGINEER
<br /> the services, , materials, and equipment CONTRACTOR 1 . ENGINEER will timely review and approve Shop
<br /> proposes to provide and to enable ENGINEER to review the Drawings and Samples in accordance with the schedule
<br /> information for the limited purposes required by paragraph of Shop Drawings and Sample submittals acceptable to
<br /> 6. 17. E. ENGINEER. ENGINEER's review and approval will be
<br /> only to determine if the items covered by the submittals
<br /> B. CONTRACTOR shall also submit Samples to will, after installation or incorporation in the Work, con-
<br /> ENGINEER for review and approval in accordance with the form to the information given in the Contract Documents
<br /> acceptable schedule of Shop Drawings and Sample submittals. and be compatible with the design concept of the
<br /> Each Sample will be Identified clearly as to material, Supplier, completed Project as a functioning whole as Indicated
<br /> pertinent data such as catalog numbers, and the use for which by the Contract Documents.
<br /> intended and otherwise as ENGINEER may require to enable
<br /> ENGINEER to review the submittal for the limited purposes 2. ENGINEER's review and approval will not extend
<br /> required by paragraph 6. 17. E. The numbers of each Sample to to means, methods , techniques, sequences , or
<br /> be submitted will be as specified in the Specifications , procedures of construction (except where a particular
<br /> means, method , technique, sequence, or procedure of
<br /> C. Where a Shop Drawing or Sample is required by the construction is specifically and expressly called for by
<br /> Contract Documents or the schedule of Shop Drawings and the Contract Documents) or to safety precautions or
<br /> Sample submittals acceptable to ENGINEER as required by programs incident thereto. The review and approval of
<br /> paragraph 2.07, any related Work performed prior to a separate Item as such will not indicate approval of the
<br /> ENGINEER's review and approval of the pertinent submittal will assembly in which the item functions.
<br /> be at the sole expense and responsibility of CONTRACTOR.
<br /> 3 . ENGINEER's review and approval of Shop
<br /> D. Submittal Procedures Drawings or Samples shall not relieve CONTRACTOR
<br /> from responsibility for any variation from the require-
<br /> 1 . Before submitting each Shop Drawing or Sam- ments of the Contract Documents unless CONTRAC-
<br /> ple, CONTRACTOR shall have determined and verified : TOR has in writing called ENGINEER's attention to