3 . 0 OPERATIONAL CONSIDERATIONS DURING DREDGING <br /> The primary objectives of site management during dredging operations are to maintain acceptable <br /> effluent quality during the decanting process , to maximize the dewatering rate of the deposited material by <br /> controlling the pattern of deposition , and to minimize the impact of the site on adjacent properties . To this <br /> end, six elements of site management are discussed : ( 1 ) placement and handling of the dredge discharge and <br /> return water pipelines, (2) operation and monitoring of the dredged slurry inlet, (3 ) operation and adjustment <br /> of the weirs , (4) monitoring of the released effluent, ( 5 ) continued monitoring of local groundwater <br /> conditions, and (6) compliance with the Jacksonville District ' s Migratory Bird Policy . <br /> 3. 1 Pipeline Placement <br /> The dredge (with additional boosters as necessary) will pump the dredged material as a slurry from <br /> the dredging site to the containment basin via pipeline . Thus, each dredging operation over the design life <br /> of Site IR- 14 will involve placing and retrieving both dredge discharge and return water pipelines . To <br /> minimize impacts to the mangrove wetlands, the dredge discharge pipeline will follow an existing graded <br /> road from near the Indian River shoreline to the road ' s intersection with the dike ' s eastern side (Figure 2 . 1 ) . <br /> The pipeline will then follow the dike ' s outside toe south and west to the basin ' s southwest corner and enter <br /> the basin by passing over the dike crest. This route will temporarily impact only a narrow fringe of <br /> mangroves at the Indian River shoreline . The return water pipeline will exit the basin near its northeastern <br /> corner and follow the same graded road to the Indian River shoreline . The return water pipeline outfall will <br /> be placed at or beyond the Indian River shoreline as necessary to minimize possible impacts to local seagrass <br /> beds . <br /> The pipelines will be placed immediately before dredging begins as part of the dredging contractor' s <br /> mobilization procedures . The dredge discharge pipeline will remain in place only during active dredging <br /> operations . The time required to complete this phase of operations Will depend on the quantity and <br /> distribution of the dredged material . As discussed previously, a 10- year dredging cycle is likely to produce <br /> a bulked volume of approximately 32 ,600 cy of material . This volume corresponds to an in situ volume of <br /> approximately 16 ,300 cy . Dredging this volume of material and transporting it to the containment basin, <br /> combined with reasonable delays associated with dredging projects of this complexity, yields an estimated <br /> 27 <br />