the agreement of the Design/Builder; an order for a minor change in the Work may be <br />issued by the Design/Builder alone. <br />§ 8.1.3 Changes in the Work shall be performed under applicable provisions of the <br />Contract Documents, and the Design/Builder shall proceed promptly, unless otherwise <br />provided in the Change Order, Construction Change Directive, or order for a minor <br />change in the Work. <br />§ 8.1.4 If unit prices are stated in the Contract Documents or subsequently agreed <br />upon, and if quantities originally contemplated are so changed in a proposed Change <br />Order or Construction Change Directive that application of such unit prices to quantities <br />of Work proposed will cause substantial inequity to the Owner or the Design/ Builder, <br />the applicable unit prices shall be equitably adjusted. <br />§ 8.2 CHANGE ORDERS <br />§ 8.2.1 A Change Order is a written instrument prepared by the Design/Builder and <br />signed by the Owner and the Design/Builder, stating their agreement upon all of the <br />following: <br />.1 a change in the Work; <br />.2 the amount of the adjustment, if any, in the Contract Sum; and <br />.3 the extent of the adjustment, if any, in the Contract Time. <br />§ 8.2.2 If the Owner requests a proposal for a change in the Work from the <br />Design/Builder and subsequently elects not to proceed with the change, a Change <br />Order shall be issued to reimburse the Design/Builder for any costs incurred for <br />estimating services, design services or preparation of proposed revisions to the <br />Contract Documents. <br />§ 8.3 CONSTRUCTION CHANGE DIRECTIVES <br />§ 8.3.1 A Construction Change Directive is a written order prepared and signed by the <br />Owner, directing a change in the Work prior to agreement on adjustment, if any, in the <br />Contract Sum or Contract Time, or both. <br />§ 8.3.2 Except as otherwise agreed by the Owner and the Design/Builder, the <br />adjustment to the Contract Sum shall be determined on the basis of reasonable <br />expenditures and savings of those performing the Work attributable to the change, <br />including the expenditures for design services and revisions to the Contract Documents. <br />In case of an increase in the Contract Sum, the cost shall include a reasonable <br />allowance for overhead and profit. In such case, the Design/Builder shall keep and <br />present an itemized accounting together with appropriate supporting data for inclusion <br />in a Change Order. Unless otherwise provided in the Contract Documents, costs for <br />these purposes shall be limited to the following: <br />.1 costs of labor, including social security, old age and unemployment <br />insurance, fringe benefits required by agreement or custom, and workers' <br />compensation insurance; <br />15 <br />