1 . 04 EXAMINATION OF CONTRACT DOCUMENTS AND SITE <br /> A . It is the responsibility of each Bidder, before submitting a bid, to (a) examine the Contract <br /> Documents thoroughly, (b) visit the site to become familiar with local conditions that may <br /> affect cost progress , performance , or furnishing of the work, (c) consider federal , state, <br /> and local laws and regulations that may affect costs, progress, performance , or furnishing <br /> of the work, (d) study and carefully correlate Bidder's observations with the Contract <br /> Documents, and (e) notify Engineer of all conflicts, errors, or discrepancies in the Contract <br /> Documents. <br /> Reference is made to the Supplementary Conditions for identification of: <br /> 1 . Those reports of explorations and tests of subsurface conditions at the site which <br /> have been utilized by Engineer in preparation of the Contract Documents . Bidder <br /> may rely upon the accuracy of the technical data contained in such reports, but not <br /> upon non-technical data, interpretations, or opinions contained therein or for the <br /> completeness thereof the purposes of bidding or construction . <br /> 2 . Those drawings of physical conditions in relation to existing surface and <br /> subsurface conditions (except underground facilities) which are at or contiguous <br /> to the site have been utilized by Engineer in preparation of the Contract <br /> Documents . Bidder may rely upon the accuracy of the technical data contained in <br /> such drawings, but not upon the completeness thereof for the purposes of bidding <br /> or construction . Copies of such reports and drawings will be made available by <br /> Owner to any Bidder on request. Those reports and drawings are not part of the <br /> Contract Documents, but the technical data contained therein upon which Bidder <br /> is entitled to rely as provided in Paragraphs 1 . 04 .B1 and 1 .04 .132 are incorporated <br /> therein by reference . Such technical data has been identified and established in the <br /> Supplementary Conditions . <br /> B . Information and data reflected in the Contract Documents with respect to underground <br /> facilities at or contiguous to the site is based upon information and data furnished to <br /> Owner and Engineer by owners of such underground facilities or others , and Owner does <br /> not assume responsibility for the accuracy or completeness thereof unless it is expressly <br /> provided otherwise in the Supplementary Conditions . <br /> C . Provisions concerning responsibilities for the adequacy of data furnished to prospective <br /> Bidders on subsurface conditions, underground facilities and other physical conditions, <br /> and possible changes in the Contract Documents due to differing conditions appear in <br /> Paragraphs 4 . 02 , 4 . 03 , and 4 .04 of the General Conditions . <br /> D . Before submitting a Bid, each Bidder will , at Bidder's own expense, make or obtain any <br /> additional examinations, investigations, explorations, tests, and studies, and obtain any <br /> additional information and data which pertain to the physical conditions (surface, <br /> subsurface and underground facilities) at or contiguous to the site or otherwise which may <br /> affect cost, progress, performance, or furnishing of the work and which Bidder deems <br /> necessary to determine its Bid for performing and furnishing the work in accordance with <br /> the time, price and other terms and conditions of the Contract Documents . <br /> 044572017 <br /> 00100-2 <br />