Laserfiche WebLink
12 . 03A and B Delete paragraphs 12 . 03 . A and 12 . 03B of the General Conditions in their entirety and <br /> replace with the following: <br /> A . Where Contractor is delayed or prevented from completing any part of the Work within the <br /> Contract Times due to delay beyond the control of Contractor, the Contract Times (or Milestones) will be <br /> extended in an amount equal to the time lost due to such delay if ( l) a Claim is made therefore as provided <br /> in paragraph 12 . 02 . A and (2) Contractor provides evidence that the delay impacted the critical path of the <br /> Project . Delays beyond the control of Contractor shall include, but not be limited to, acts or neglect by <br /> Owner, acts or neglect of utility owners or other contractors performing other work as contemplated by <br /> Article 7 , fires, floods, abnormal weather conditions or acts of God . The Contractor must request the <br /> extension of time in writing and must provide the following information within the time periods stated <br /> hereafter. Failure to submit such information and in compliance with the time requirements hereinafter <br /> stated, shall constitute a waiver by the Contractor and a denial of the claim for extension of time : <br /> 1 . Nature of the delay or change in the Work; <br /> 2 . Dates of commencement and cessation of the delay or change in the Work; <br /> 3 . Activities on the current progress schedule affected by the delay or change in the Work; <br /> 4 . Identification and demonstration that the delay or change in Work affects the critical path; <br /> 5 . Identification of the source of delay or change in the Work; <br /> 6 . Anticipated extent of the delay or change in the Work; and <br /> 7 . Recommended action to minimize the delay. <br /> B . Contractor hereby affirms that the extension of time granted herein is the Contractor's sole and exclusive <br /> remedy. Apart from extension of time, no payment or claim for damages shall be made to the Contractor as <br /> compensation for damages for any delays or hindrances from any cause whatsoever in the progress of the <br /> Work whether such delay is avoidable or unavoidable . <br /> SC 12 . 03C Delete paragraph 12 . 03 . 0 of the General Conditions in its entirety. <br /> SC 12 . 03D Delete paragraph 12 .03D of the General Conditions in its entirety and replace with the <br /> following : <br /> In no event shall Owner, Engineer, or the Related Entities of either of them be liable to Contractor, any <br /> Subcontractor, any Supplier, any other person or organization, or any surety for or employee or agent of <br /> any of them, for any claim, cost, loss, or damages of any nature whatsoever arising out of or resulting from <br /> delays . <br /> ARTICLE 13 - TESTS AND INSPECTIONS ; CORRECTION, REMOVAL OR ACCEPTANCE OF <br /> DEFECTIVE WORK <br /> SC 13 . 04C . Delete paragraph 13 . 04 . 0 of the General Conditions in its entirety and replace with the <br /> following: . <br /> If it is found that the uncovered Work is defective, Contractor shall pay all claims, costs, losses, and <br /> damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other <br /> professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such <br /> uncovering, exposure, observation, inspection, and testing, and of satisfactory replacement or <br /> reconstruction (including but not limited to all costs of repair or replacement of work of others) ; and <br /> Owner shall be entitled to an appropriate decrease in the Contract Price . <br /> SC 13 . 04D . Delete paragraph 13 .04 .D of the General Conditions in its entirety and replace with the <br /> 044572017 <br /> 00800- 13 <br />