Laserfiche WebLink
SC -6.0213 Add the following new paragraphs immediately after paragraph 6.02B. of the General <br />Conditions which are to read as follows: <br />C. Regular working hours are defined as 8 hours per day, Monday through Friday, excluding holidays, <br />between the hours of 7:00 AM and 7:00 PM. Requests to work other than regular working hours shall be <br />submitted to Engineer not less than 48 hours prior to any proposed weekend work or scheduled extended <br />work weeks. Occasional unscheduled overtime on weekdays may be permitted provided two hours notice <br />is given to Engineer. <br />D. Contractor shall reimburse the Owner for additional engineering and/or inspection costs incurred as a <br />result of overtime work in excess of the regular working hours stipulated in Article SC -6.02C. At Owner's <br />option, overtime costs may either be deducted from the Contractor's monthly payment request or deducted <br />from the retainage prior to release of final payment. Overtime costs for the Owner's personnel shall be <br />based on the individual's current overtime wage rate. Overtime costs for personnel employed by the <br />Engineer or Owner's independent testing laboratory shall be calculated in accordance with the terms of <br />their respective contracts with the Owner. <br />SC 6.04A.1 Add the following sentence immediately after the existing text in paragraph 6.04 A.1 of the <br />General Conditions: <br />Additionally, any and all changes to the Project's critical path must be reflected in each Project schedule. <br />SC -6.04.A.3 Add the following paragraph immediately after paragraph GC -6.04.A.2 of the General <br />Conditions: <br />Contractor shall give Owner full information in advance as to its plans for performing each part of the Work. If <br />at any time during the progress of Work, Contractor's actual progress is inadequate to meets the requirements <br />of the Contract, Owner may, but is not obligated to, so notify Contractor. In such event, Contractor <br />acknowledges and agrees that Contractor shall implement some or all of the following remedial actions at the <br />sole cost and expense of Contractor: (a) Increase manpower in such quantities and crafts as necessary to <br />eliminate the backlog of Work; (b) Increase the number of working hours per shift, shifts per working day, <br />working days per week, the amount of construction equipment, or any combination of the foregoing to <br />eliminate the backlog of Work; or (c) Reschedule the Work in conformance with the specification <br />requirements. Neither such notice by Owner nor Owner's failure to issue such notice shall relieve Contractor of <br />its obligation to achieve the quality of Work and rate of progress required by the Contract. Failure of <br />Contractor to implement some or all of the remedial actions may be grounds for determination by Owner that <br />Contractor is not prosecuting its Work with such diligence as will assure completion within times specified. <br />Upon such determination, Owner may terminate Contractor's right to proceed with the performance of the <br />Contract, or any separable part thereof, in accordance with the applicable provisions of this Contract. <br />SC -6.06A <br />Delete Paragraph 6.06A of the General Conditions in its entirety and replace with the following: <br />A. Contractor shall not employ any Subcontractor, Supplier or other person or organization, (including <br />those who are to furnish the principal items of materials or equipment), whether initially or as a substitute, <br />against whom Owner may have reasonable objection. Acceptance of any Subcontractor, Supplier or other <br />person or organization by Owner shall not constitute a waiver of any right of Owner to reject defective <br />044572017 <br />00800-8 <br />