5 . Such request is for information only, and is not an instruction to execute the <br /> changes, nor to stop work in progress . <br /> B . Contractor may initiate changes by submitting a written notice to Engineer, containing: <br /> 1 . Description of the proposed changes <br /> 2 . Statement of the reason for making the changes . <br /> 3 . Statement of the effect on the Contract Sum and the Contract Time _ <br /> 4 . Statement of the effect on the work of separate contractors . <br /> 5 . Documentation supporting any changes in Contract Sum or Contract Time , as <br /> appropriate . <br /> 1 .05 CONSTRUCTION CHANGE AUTHORIZATION <br /> A. In lieu of Proposal Request, Engineer may issue a "Work Directive Change" for <br /> Contractor to proceed with a change for subsequent inclusion in a Change Order . <br /> B . Authorization will describe changes in the work, both additions and deletions , with <br /> attachments of revised Contract Documents to define details of the change . <br /> C . Owner and Engineer will sign and date the Work Directive Change as authorization for <br /> the Contractor to proceed with the Changes . <br /> 1 .06 DOCUMENTATION OF PROPOSALS AND CLAIMS <br /> A. Support each quotation for a lump sum proposal, and for each unit price which has not <br /> previously been established, with sufficient substantiating data to allow Engineer to <br /> evaluate the quotation. <br /> B . On request, provide additional data to support time and cost computation including the <br /> following: <br /> L Labor required. <br /> 2 . Equipment required. <br /> 3 . Products required: <br /> a. Recommended source of purchase and unit cost. <br /> b . Quantities required. <br /> 4. Taxes, insurance bonds. <br /> 5 . Credit for work deleted from Contract, similarly documented. <br /> 6 . Overhead and profit. <br /> 7 . Justification for any change in Contract Time, <br /> C. Support each claim for additional costs, and for work done on a time-and-material / force <br /> account basis, with documentation as required for a lump sum proposal, plus the <br /> following additional information: <br /> 1 . Name of the Owner's authorization agent who ordered the work, and date of the <br /> order. <br /> 2. Dates and time work performed, and by whom <br /> 3 . Time record, summary of hours worked, and hourly rates paid. <br /> 4 . Receipts and invoices for: <br /> a. Equipment used, listing dates and times of use. <br /> b . Products used, listing quantities . <br /> C . Subcontracts . <br /> 044572017 <br /> l <br /> 01035 -2 <br />