SECTION 02065 <br />DEMOLITION <br />PART 1 - GENERAL <br />1.01 SCOPE OF WORK <br />A. The Contractor shall furnish all supervised labor, materials, equipment, and incidentals <br />required for the removal of high service pumps (HSP) no. 1, 2, and 3 for installation of <br />new HSP. <br />B. The Contractor shall furnish all supervised labor, materials, equipment, and incidentals <br />required for the partial removal of the existing chemical room wall. <br />C. The Contractor shall furnish all supervised labor, materials, equipment, and incidentals <br />required for the removal of any pavement, including base material, as shown on the <br />construction plans. <br />D. The Contractor shall furnish all supervised labor, materials, equipment, and incidentals <br />required for the removal and the replacement of the existing roof panel of the <br />hydrofluorosilicic storage area. <br />Removal procedures are as outlined below: <br />1. Complete or partial removal and disposal of specified existing piping, mechanical <br />equipment, electrical equipment and miscellaneous appurtenances encountered <br />during construction operations. <br />2. Temporary modification of structures, equipment, appurtenances and utilities as <br />necessary to allow for operation of the facilities during construction. <br />3. Demolition, partial removal and cutting of existing concrete structure as required for <br />the new construction. <br />4. Handling of existing equipment to be reinstalled or salvageable as specified. <br />5. Off-site disposal of excess and unacceptable, materials including but not limited to <br />concrete, concrete blocks, and bricks. All materials to be disposed of in a legal <br />6. This section may not cover all of the activities necessary to perform the work. The <br />Contractor shall exercise due concern for the utility system operation and shall <br />diligently direct all of the Contractor's activities toward maintaining continuous <br />operation of the existing facilities and minimizing operation impacts. <br />1.02 CONDITION OF STRUCTURES <br />044572017 <br />02065-1 <br />