1, 13 TESTS <br />A. Test all systems in the presence of the Engineer and repair or replace all defective work. Make <br />all necessary adjustments to the systems and instruct the Owner's personnel in the proper <br />operation of the systems. <br />B. Subsystem testing shall occur after the proper operation of alarm and status contacts has been <br />demonstrated or otherwise accepted by the Engineer and after process control devices have been <br />adjusted as accurately as possible. It is intended that the Contractor will adjust level switches to <br />their operating points prior to testing and will set timing relays and/or adjust programming as <br />dictated by operating results. Subsystems, in the context discussed here, shall mean individual <br />and groups of pumps. <br />1. After initial settings have been completed, each subsystem shall be operated in the <br />manual mode and it shall be demonstrated that operation is in compliance with the <br />Contract Documents. Once the manual mode of operation has been proven, automatic <br />operation shall be demonstrated to verify such items as proper start and stop sequence of <br />pumps, etc. <br />2. Motor operated pumps shall be operated only after having been phased and tested for <br />correct motor rotation and current draw by a representative of the pump Manufacturer. <br />Tests shall verify status indication, and correct command control from local and remote <br />devices. <br />END OF SECTION <br />044572017 <br />16050-5 <br />