1 . 6 REMOVAL OF TEMPORARY CONSTRUCTION FACILITIES
<br /> Remove the various temporary facilities , services , and controls and legally dispose of
<br /> them as soon as the work is complete . The areas of the site used for temporary
<br /> facilities shall be properly reconditioned and restored to a condition acceptable to the
<br /> OWNER .
<br /> w SECTION 01541 PROTECTION OF THE WORK AND
<br /> PROPERTY
<br /> 1 . 1 GENERAL
<br /> A . CONTRACTOR shall be responsible for taking all precautions , providing all
<br /> programs , and taking all actions necessary to protect the Work and all public and
<br /> private property and facilities from damage as specified in the General Conditions
<br /> and herein .
<br /> . B . In order to prevent damage , injury or loss , CONTRACTOR ' S actions shall include ,
<br /> but not be limited to , the following :
<br /> 1 . Store apparatus , materials , supplies , and equipment in an orderly , safe
<br /> manner that will not unduly interfere with the progress of the Work or the
<br /> Work of any other Contractor or utility service company .
<br /> 2 . Provide suitable storage facilities for all materials , which are subject to injury by
<br /> exposure to weather , theft , breakage , or otherwise .
<br /> 3 . Place upon the Work or any part thereof , only such loads as are consistent
<br /> with the safety of that portion of the Work .
<br /> 4 . Clean up frequently all refuse , rubbish , scrap materials , and debris caused by
<br /> construction operations , so that at all times , the site of the Work presents a
<br /> safe , orderly , and workmanlike appearance .
<br /> 5 . Provide barricades and guard rails around openings , for scaffolding , for
<br /> temporary stairs and ramps , around excavations , elevated walkways and
<br /> other hazardous areas .
<br /> C . Except after written consent from proper parties , do not enter or occupy
<br /> privately- owned land with men , tools , materials or equipment , except on
<br /> easements provided herein .
<br /> D . Assume full responsibility for the preservation of all public and private property or
<br /> facility on or adjacent to the site . If any direct or indirect damage is done by or on
<br /> account of any act , omission , neglect or misconduct in the execution of the Work
<br /> by the CONTRACTOR , it shall be restored by the CONTRACTOR , at its expense ,
<br /> to a condition equal to or better than that existing before the damage was done .
<br /> 1 . 2 BARRICADES AND WARNING SIGNALS
<br /> Where Work is performed on or adjacent to any roadway , right- of-way , or public
<br /> place , provide barricades , fences , lights , warning signs , danger signals , and
<br /> watchmen , and take other precautionary measures for the protection of persons or
<br /> property and of the Work . Paint barricades so they are visible at night . From sunset
<br /> to sunrise , furnish and maintain at least one light at each barricade . Erect sufficient
<br /> barricades to keep vehicles from being driven on or into Work under construction .
<br /> Furnish watchmen in sufficient numbers to protect the Work . CONTRACTOR ' s
<br /> GENERAL REQUIREMENTS
<br /> GR - 11
<br /> FAPublic Works\Capital Projects\Oslo Road Lateral ABID DOCUMENTS\DIVISION 1 - General Requirements . doc
<br /> y. 5/23/01