® ' <br /> determine the quantity of labor on the job in order to meet the predetermined <br /> schedules . <br /> 5 . State your experience in cost loading of schedules . <br /> Ocean Gate has the ability to produce cost loaded schedules and typically submits this <br /> documentation for clients upon request. We do not recommend this method for <br /> several reasons : accuracy issues; alignment of subcontractor scheduled values is <br /> impractical when building a project schedule; and it is easy for a Contractor to front <br /> end load costs associated to a project which creates the potential of overcharging. <br /> In general, Ocean Gate monitors and controls cost in detail with weekly labor reports <br /> and monthly material reports. The assigned Project Superintendent is responsible for <br /> maintaining the quantities and labor by cost coding each labor report. This <br /> information can then be accessed on our website once the client has logged in. <br />