Laserfiche WebLink
determine the quantity of labor on the job in order to meet the predetermined <br />schedules. <br />5. State your experience in cost loading of schedules. <br />Ocean Gate has the ability to produce cost loaded schedules and typically submits this <br />documentation for clients upon request. We do not recommend this method for <br />several reasons: accuracy issues; alignment of subcontractor scheduled values is <br />impractical when building a project schedule; and it is easy for a Contractor to front <br />end load costs associated to a project which creates the potential of overcharging. <br />In general, Ocean Gate monitors and controls cost in detail with weekly labor reports <br />and monthly material reports. The assigned Project Superintendent is responsible for <br />maintaining the quantities and labor by cost coding each labor report. This <br />information can then be accessed on our website once the client has logged in, <br />