The scale is incorrect on sheets E101 . Correct scale is 1 " = 20 '. <br /> 6 , CONCRETE POLES , FiXTURE SCHEDULE CALLS FOR 12 ' AFG , WHAT IS THE TOTAL <br /> - REQUIRED LENGTH OF THE POLE ? WHAT ARE THE WIND LOAD REQUIREMENTS AND <br /> ARE LOAD CALCULATIONS AND ENGINEERING REQUIRED? <br /> The site poles must be buried per the wind load calculations that must be provided by the pole <br /> manufacturer. The wind load shall be at least 140 MPH. See Structural Drawings for exact wind load <br /> requirements . <br /> 7 WHO PROVIDES HAND DRYERS ? <br /> Hand Dryers will be furnished and installed by the CONTRACTOR. <br /> 8 , UPON EXAMINATION OF THE ELECTRICAL PLANS IT WAS FOUND THE ONE - LINE RISER <br /> DIAGRAM SHOWS A 100 AMPERE MAIN CIRCUIT BREAKER , THE WIRE SIZE ALSO <br /> FIGURES TO BE 100 AMPERE . PANEL LP - 1 SHOWS A MAIN CIRCUIT BREAKER SIZE OF <br /> 200 AMPERE , IT APPEARS FROM THE CALCULATED LOAD OF 62 AMPERES , THAT 100 <br /> AMPERES IS CORRECT . PLEASE CONFIRE THE CORRECT AMPERAGE . <br /> The panel size will be 100-amp main breaker. <br /> 9 . IS IT THE CONTRACTOR ' S RESPONSIBILITY TO PROVIDE CONDUIT FOR THE TELEPHONE <br /> SERVICE TO THE LIFEGUARD STATION ? IF SO , DOES THAT ORIGINATE FROM THE <br /> NORTHWEST CORNER OF THE PROPERTY ? <br /> Telephone service shalt be provided via a 1 " conduit at 1 ft below grade from the nearest telephone pale with <br /> telephone service to lifeguard stand or alternately the Contractor may attempt to locate and splice into the <br /> existing conduit, as approved by the Engineer. See sheet U- 1 REVISED for the location of known existing <br /> telephone service . ADDITIONALLY: The phone line is a direct burial line. AT& T will need to pull their <br /> line to the existing lifeguard stand to a new demarcation point (maybe the side of the new <br /> restrooms) . From there the contractor will be responsible for the new line to the new lifeguard stand <br /> location . <br /> 10 . WILL FP & L PULL SERVICE WIRE THROUGH CONDUIT INSTALLED BY CONTRACTOR OR <br /> WILL CONTRACTOR BE REQUIRED TO PROVIDE BOTH ? <br /> FPL will provide and install a hand hole at the base of the concrete pole and install wire and <br /> conduit up the pole to the transformer. The CONTRACTOR is responsible for running conduit <br /> and wiring from the hand hole to the electrical meter can as shown on the electrical site plan <br /> drawing. <br /> 11 . C-2 , PLEASE PROVIDE A DETAIL FOR THE NEW 18 ' GATE AT THE NEW 6 ' FENCE LINE . <br /> Please see Technical Specification SECTION 020821 for gate and fence detail. <br /> 12 . C-2 , PLEASE PROVIDE THE QUANTITY AND A DETAIL FOR THE 12 " DIAMETER BOLLARD . <br /> ALSO VERIFY THAT 12" ROUND IS CORRECT . <br /> Contractor shall install (per manufactures specifications) seven (7) 42 "- 5 % diameter Pour In Place <br /> Bollards as supplied by Stor- Quip Systems, Inc or as approved by engineer. <br /> 13 . C- 2 , PLEASE PROVIDE ELEVATIONS AND DETAIL FOR THE CONCRETE SIDEWALK/PLAZA <br /> WHERE IT ABUTS THE ASPHALT PARKING AND HANDICAP SPACES . <br /> The concrete sidewalk/plaza will be flush against the asphalt parking surface. Grading east of the <br /> asphalt shall slope evenly to meet grades noted at the base of the stairs to the boardwalk and <br /> restrooms. <br /> 14 . C-2 , PLEASE PROVIDE SPECIFICATIONS AND QUANTITIES FOR ALL SITE FURNISHINGS . <br /> • Curb stops - 39 <br /> • Signs One-Way - 1 , Do Not Enter - 4, STOP - 2 . and Handicap - 4 <br /> • Bollards - 7 <br /> F :\Public Works\Cliff Suthard\Wabasso Beach Park\A Construction Bid Documents\Bid Documents as of 2-6-2008Wdde Page 510 #21#3 , #4 , & <br /> #5\ADDENDUM #2 AND ATTACHMENTS\Addendum #2 .doc <br /> Rev. 3- 12-08 <br />