The exhaust fans shall be tied into the lighting circuit in the appropriate bathroom. <br /> 36 . P1 . 10 , THE OUTDOOR SHOWER DETAIL STATES , TIE DRAIN INTO NEAREST STORM <br /> DRAINAGE , REFER TO CIVIL DRAWINGS , THE CIVIL DRAWINGS ARE ABSENT IN THIS <br /> REGARD , PLEASE PROVIDE A DETAIL DRAWING , QUANTITY AND ETC . <br /> There are no proposed storm drains in the vicinity of the shower, therefore, the Contractor <br /> shall be grade shower area such that the shower will drain into a slightly depressed area below the <br /> boardwalk. <br /> 37 . E1 . 01 and E1 . 02 , THE SITE PLAN SHOWS THE SCALE AT %" PER FOOT , IS THIS CORRECT? <br /> The scale is incorrect on sheets E1 . 01 and E1 . 02. Correct scale is 1 " = 20'. <br /> 38 , SPECIFICATIONS BOOK REFERS TO SHEET E3 . 10 FOR ELECTRICAL SPECIFICATIONS , <br /> PLEASE VERIFY THIS SHEET EXISTS , <br /> In the contract documents, in Section 00010, TABLE OF CONTENTS, sheet 000104, in DIVISION 16 <br /> - ELECTRICAL, revise the notation "See Drawing Sheet E3. 10 " to read: <br /> " See Drawing Sheet E3 . 00 " . <br /> Revised TABLE OF CONTENTS sheet 00010411 is attached . <br /> 39 . FINISH SCHEDULE ON A-6 . 10 SHOWS NO FINISHES HOWEVER ON A-4 . 20 PAVILLION WALL <br /> SECTIONS SHOWS THAT THE PAVILLION HAS AREAS TO BE PAINTED . <br /> Section 09911 -EXTERIOR/INTERIOR PAINTING, 3. 5, EXTERIOR PAINTING SCHEDULE. Specification <br /> calls out all areas to be painted. <br /> 40 . C-2 SHOWS THAT BOLLARDS ARE PLACED 6" O . C . IS THIS CORRECT OR IS IT TO BE 6 ' <br /> O . C . ? <br /> Bollards are to be installed at 6 feet on center. <br /> 41 . C-7 SECTION B-B SHOWS 2X12 BEAM BOLTED TO 6X6 PILE : ANCHOR DETAIL-SHOWS <br /> 2X10 BEAM — PLEASE CLARIFY BEAM SIZE . <br /> The beam should be 2 "x12 ". <br /> 42 . C-2 SHOWS A TYPE F CONCRETE CURB ON EAST SOIDE BUT SECTION A-A, C-3 HAS THE <br /> CURB LISTED AS TYPE D . <br /> The curb on the eastern edge of pavement shall be a type F curb. <br /> 43 . C-6 BOARDWALK & ADA RAMP TYPICAL DETAIL: THE DECKING IS SHOWN AS BEING <br /> NAILED AT ONE LOCATION BUT SCREWED IN ANOTHER = PLEASE CLARIFY <br /> ATTACHMENT OF DECKING . <br /> The decking is to be screwed, please see Technical Specification SECTION 03000 for boardwalk <br /> construction methodology. <br /> 44 . A4 . 20 PAVILLION WALL SECTION " PAINT EXPOSED CONSTRUCTION " —DOES THIS <br /> INCLUDE UNDERSIDE OF PLYWOOD DECK AND EXPOSED TRUSSES ? <br /> Section 09911 —EXTERIORIINTERIOR PAINTING, 3. 5, EXTERIOR PAINTING SCHEDULE. Specification <br /> calls out all areas to be painted, which includes underside of plywood sheathing and trusses . <br /> 45 . SHEET LA- 1 SOUTH END OF PROPERTY SHOWS LANDSCAPING ALONG DISNEY RESORT <br /> BORDER , HOWEVER SHEET ASO , 10 SHOWS A NEW SIDEWALK BEING INSTALLED ; <br /> PLEASE CLARIFY WHAT IS GOING AT THIS LOCATION . <br /> Revised DRAWING Sheet LA- 1 REVISED is attached. <br /> 46 . PLEASE GIVE LOCATION OF FLAGPOLE . <br /> Flagpole shall be located in the center of the circular bench area. Delete CE Green Buttonwood tree, <br /> ground cover to remain. <br /> F :\Public Works\Cliff Suthard\Wabasso Beach Park1A Construction Bid Documents\Bid Documents as of 2-6-2008\Adde dum Page 810#11 #3 , #4 , & <br /> #5\ADDENDUM #2 AND ATTACHMENTS\Addendum #2.doc <br /> Rev . 3-12-08 <br />