L . If a submittal is unacceptable , three (3 ) copies will be returned to <br /> CONTRACTOR with one of the following notations : <br /> 1 . " Revise and Resubmit" <br /> 2 . " Not Approved " <br /> M . Upon return of a submittal marked " Revise and Resubmit" , make the corrections <br /> indicated and repeat the initial approval procedure . The " Not Approved " notation <br /> is used to indicate material or equipment that is not acceptable . Upon return of a <br /> submittal so marked , repeat the initial approval procedure utilizing acceptable <br /> material or equipment . <br /> N . Any related Work performed or equipment installed without an "Approved " or <br /> "Approved as Corrected " Shop Drawing or Design Drawing will be the sole <br /> responsibility of the CONTRACTOR . <br /> O . Submit Shop Drawings or Design Drawings well in advance of the need for the <br /> material or equipment for construction and with ample allowance for the time <br /> required to make delivery of material or equipment after data covering such is <br /> „ approved . CONTRACTOR shall assume the risk for all materials or equipment , <br /> which are fabricated or delivered prior to the approval of Shop Drawings . <br /> Materials or equipment will not be included in periodic progress payments until <br /> approval thereof has been obtained in the specified manner. <br /> P . ENGINEER will review and process all submittals promptly , but a reasonable <br /> time should be allowed for this , for the Shop Drawings or Design Drawings being <br /> revised and resubmitted , and for time required to return the approved Shop <br /> Drawings or Design Drawings to the CONTRACTOR . <br /> Q . Furnish required submittals with complete information and accuracy in order to <br /> achieve required approval of an item within three submittals . All costs to <br /> ENGINEER or ENGINEER' s CONSULTANT involved with subsequent submittals <br /> of Shop Drawings , Samples or other items requiring approval , will be <br /> backcharged to CONTRACTOR in accordance with the General Conditions and <br /> the Supplementary Conditions . If the CONTRACTOR requests a substitution for <br /> a previously approved item , all of ENGINEER'S and ENGINEER' s <br /> CONSULTANT ' s costs in the reviewing of the substitution will be backcharged to <br /> CONTRACTOR unless the need for such substitution is beyond the control of <br /> CONTRACTOR . <br /> + + END OF SECTION + + <br /> Last Revised 12/2007 01340-6 Wabasso Beach Pk Restoration <br /> FAPublic Works\Cliff Suthard\Wabasso Beach Park\A Construction Bid Documents\Bid Documents as of 1 -9-2008\Technical <br /> Specifications\Div 1 \01340 - Submittal of Shop Drawings , Product Data, and Samples .doc <br />