Laserfiche WebLink
Task 3.2 – Foreemain Design <br /> The Consultant will prepare design drawings of the proposed forcemain piping after the size has <br /> been determined. Existing utility information provided by IRCU and others will be used in <br /> conjunction with the survey and underground locate information as a basis for design of the <br /> piping alignment. Technical specifications will be based on the Owners current Utility <br /> Standards. <br /> Preparation of final construction drawings will consist of plan sheets with survey information, <br /> key sheets, and details. The forcemain design drawings will be plan only view (no profile) with <br /> 1 -inch= 40- feet scale drawings with a two-pane view, with exception of up to six plan and <br /> profile drawings for the locations that cross intersections or canals. Detailed drawings of <br /> specific construction items that may be required for this project will be provided on one sheet. <br /> IRCU Standard detail sheets will consist of up to three sheets. There will be approximately 31 <br /> drawings, which will consist of the following sheets : <br /> • Cover with site location map, one ( 1 ) sheet <br /> • Overall project, one ( 1 ) sheet <br /> • General information, one ( 1 ) sheet <br /> • Horizontal plan views of alignment, eighteen ( 18) sheets <br /> • Plan and profiles for intersections and canal crossings, six (6) sheets <br /> • Specific details, one (1 ) sheet <br /> • IRCU standard details, three (3) sheets <br /> Consultant will attend the following meetings to discuss the objectives and progress of the <br /> project and design requirements specific to this project: <br /> • Kick-off meeting (held concurrently with the re-pump station design Kick-off meeting) <br /> • Progress meeting at 60% completion <br /> • Progress meeting at final completion <br /> The Consultant will submit four (4) full size sets of drawings at 60% completion and final <br /> completion. The revisions to the forcemain design requested by the Owner will be made based <br /> on comments received by the Consultant at the meetings, described above. The Consultant can <br /> provide additional design submittals and attend additional meetings related to forcemain design <br /> as Additional Services . <br /> Task 3 .2 — Re-Pump Station Design <br /> Pump station design will consist of preparation of construction plans and specifications <br /> consisting of the following sheets : <br /> • Cover with site location map, one ( 1) sheet <br /> • Overall project key sheet, one ( 1 ) sheet <br /> • General information, one ( 1 ) sheet <br /> • Horizontal control plan of design drawings, one ( 1 ) sheets <br /> • Plan and profiles of the re-pump station, two (2) sheets <br /> • Mechanical drawings, two (2) sheets <br /> • Structural Plans , Sections and Details, four (4) sheets <br /> F :AUtilitiesVUfIL.ITY - ENGINEERINGAProjects - Utility Construction PermitsVIRC - 8th Street FM Ext from IR BIv to 58th Av <br /> - UCP 2628 Work Order No. 12 to KFI&AAA - Work Order No. 12 - March 29, 2006.doc <br /> Page 5 of I 1 <br />