associated with the overflow / storage area and adjusting the trailer entrance road and lift <br /> station. <br /> The requested budget amendment for Subtask 1 . 5 is included in Table 1 . <br /> TASK 2. 0 - PERMITTING ASSISTANCE <br /> Based on the comments and requirements received from the Community Development <br /> Department during the Site Plan Permit pre- application meeting, the following additional <br /> permits will be required : <br /> ® IRC Right of Way Permit, <br /> ® IRC Concurrency Determination, <br /> • IRC Utilities Construction Permit, <br /> ® IRFWCD Application for Utility Construction Permit, and <br /> s FDEP Application for Constructing a Domestic Wastewater System. <br /> This task provides for the preparation of the additional permit applications, meetings, and. <br /> negotiation with the permitting agencies and preparation of responses to Requests for <br /> Additional Information (RAI) for the permits listed above . These additional permits were not <br /> included in the original Scope of Services . The requested budget amendment for Task 2 is <br /> included in Table 1 . <br /> PHASE II - CONSTRUCTION SERVICES <br /> TASK 5. 0 - GENERAL ENGINEERING SERVICES <br /> The construction time of the new Oslo Convenience Center is estimated to be 9 months due to <br /> the required driven pile system and retaining wall system and the addition of the lift <br /> station / forcemain, canopy, and security systems . Under this task, CDM will provide additional <br /> construction services on an as needed basis during construction for the estimated 9-month <br /> construction period (240 days to substantial completion and 270 days to final acceptance ) . <br /> Subtask 5. 3 Shop Drawings <br /> CDM will review and approve Shop Drawings and samples, the results of tests and inspections <br /> and other data which the Contractor is required to submit for the lift station and forcemain, <br /> office / household hazardous waste building, security camera system, and the free standing <br /> entry sign . <br /> Subtask 5.4 RFI/Clarification <br /> CDM will provide response to request for information with regard to the driven pile system, lift <br /> station and forcemain, office / household hazardous waste building, security camera system, <br /> and the free standing entry sign. CDM will issue IRC SWDD instructions to the Contractor and <br /> issue necessary interpretations and clarifications of the Contract Documents . Have authority as <br /> IRC SWDD' s representative, to require special inspection or testing of the work . Act as initial <br /> A-4 i12572. doc <br />