22 . SPECIAL PROVISIONS <br /> The Contractor shall comply with the following special provisions as part of the contract for the <br /> 8th St . Sidewalk Improvements Between U . S . 1 and 6th Ave . Project : <br /> ( 1 ) (A) BASE BID - TIMEFRAME <br /> The total time for the project construction will commence with a Written Notice to <br /> Proceed from the County that is anticipated to be issued to the Contractor on <br /> XXXX XX , 2010 with the project being substantially completed by the Contractor <br /> on XXXX XX , 2010 and totally 100 % completed by the Contractor on XXXXX <br /> XX , 2010 . <br /> ( B ) CPM SCHEDULE AND NARRITIVE <br /> The Contractor shall submit to the County as part of his bid submission , a <br /> detailed construction schedule in CPM format outlining the proposed progress of <br /> the work to be performed by the Contractor and his subcontractors for the BASE <br /> BID — TIMEFRAME . <br /> The Contractors CPM schedule for the BASE BID — TIMEFRAME shall include <br /> but not be limited to the demolition phasing dates of the work , manufacturing <br /> dates of all components , all phasing dates of the total work required for each <br /> component to be manufactured and installed , the start and completion dates for <br /> each phase of the individual components to be installed , street closure dates and <br /> durations including the start and completion dates of each phase . <br /> In addition to the CPM schedule for the BASE BID — TIMEFRAME , the <br /> Contractor shall submit , in narrative format , a detailed description of the means <br /> and methods for the Contractor' s work including but not limited to the <br /> mobilization and demobilization of all equipment and materials , the demolition <br /> sequencing of the work , the individual phasing sequencing of each component <br /> manufacturing and installation , the Contractor' s proposed manpower and <br /> equipment allocations and commitments for each phase of the work , the <br /> Contractor' s proposed work hours for each day to be worked , the phasing of <br /> road closures with their closure dates and durations , work sequence and days of <br /> the week the Contractor and his subcontractors will require from the County to <br /> complete the work within the time frames of the BASE BID — TIMEFRAME . <br /> The CPM schedules for the BASE BID — TIMEFRAME and narrative approach <br /> for the project will be used by the County in determining the best value in <br /> awarding the construction contract . <br /> The contractor will not be allowed to change his submitted CPM schedule for the <br /> BASE BID — TIMEFRAME prior to and or after the Award of Contract and the <br /> Notice to Proceed is issued by the County without prior written approval of the <br /> County' s Project Manager . <br /> ( 2 ) The Contractor shall provide daily clean up of the project work area . Cleanup shall <br /> 58 <br /> 12J29/2009 2:23:44 PM <br />