completion date under the provisions of this contract, the Owner ' s determination as to the <br /> total number of days of extension shall be based upon the currently approved schedule <br /> and on all data relevant to the extension . Such data shall be included in the next monthly <br /> updating of the schedule . The Contractor acknowledges and agrees that actual delays in <br /> activities which , according to the schedule, do not affect any contract completion date <br /> shown by the critical path in the schedule do not have any affect on the contract <br /> completion date or dates , and therefore , will not be the basis for a change therein . <br /> F . From time to time it may be necessary for the contract schedule and/or completion time <br /> to be adjusted by the Owner to reflect the effects of job conditions, weather, technical <br /> difficulties , strikes , unavoidable delays on the part of the Owner or his representatives , <br /> and other unforeseeable conditions which may indicate schedule adjustments acid/or <br /> completion time extension . Under such conditions, the Contractor shall reschedule the <br /> work and/or contract completion time to reflect the changed conditions and the <br /> Contractor shall revise his schedule accordingly . No additional compensation shall be <br /> made to the Contractor for such schedule changes except for unavoidable overall contract <br /> time extensions beyond the actual completion of all unaffected work in the contract, in <br /> which case the Contractor shall take all possible action to minimize any time extension <br /> and any additional cost to the Owner . It is specifically pointed out that the use of <br /> available float time in the schedule may be used by the Owner as defined by the <br /> Engineer, as well as by the Contractor . Float time is defined as the amount of time <br /> between the early start date, and the late start date, or the early finish date and the late <br /> finish date, of any of the activities in the schedule . <br /> G . The Owner controls the float time in the approved schedule and , therefore, without <br /> obligation to extend either the overall completion date or any intermediate completion <br /> dates set out in the schedule , the Owner may initiate changes to the contract work that <br /> absorb float time only . Owner- initiated changes that affect the critical path on the <br /> approved schedule shall be the sole grounds for extending (or contracting) said <br /> completion dates . Contractor- initiated changes that encroach on the float time identified <br /> in the approved schedule may be accomplished with the Owner ' s concurrence . Such <br /> changes , however, shall give way to Owner- initiated changes competing for the same <br /> float time . <br /> 3 . 03 COORDINATING SCHEDULES WITH OTHER CONTRACT SCHEDULES <br /> A . Where work is to be perfonned under this contract concurrently with and/or contingent <br /> upon work performed on the same facilities or area under other contracts , the <br /> Contractor ' s schedule shall be: coordinated with the schedules of the other contracts . The <br /> Contractor shall obtain the schedules of the other appropriate contracts from the Owner <br /> for the preparation and updating of his schedule and shall make the required changes in <br /> his schedule when indicated by changes in corresponding schedules . <br /> END OF SECTION <br /> 01311 - 4 <br />