<br /> B . Pipe : Measurement of pipe shall be computed using linear feet, as measured along
<br /> the centerline of the pipe installed ( Except when included in lump sum bid items -ie ;
<br /> Aerial crossing) . No deduction will be made for the length of valves and fittings
<br /> installed in the line . Where the measurement terminates at a valve, bend , tee, or other
<br /> fitting, the centerline of the valve or fitting shall be the point of termination . All
<br /> required erosion control clearing, excavation , backfill , compaction , all restoration and
<br /> replacement, paving, grading, density testing , pipe lining, coating, encasement
<br /> material , restraining devices , and all mechanical joint fittings and thrust blocks shall
<br /> be included in the cost of the pipe .
<br /> C . Fittings : Measurement of cast iron and ductile iron fittings shall be on the basis of
<br /> weight. The weights used to determine the quantity installed shall be the weights of
<br /> the appropriate fittings as listed in the supplier ' s invoice or catalog . When
<br /> mechanical joint fittings are required, the weight of the gland bolts and gaskets shall
<br /> not be added to the listed weight of the fittings . Where flanged fittings are furnished,
<br /> the weight of the bolts and gaskets shall not be included .
<br /> D . Gate Valves, air release valves , Tapping Sleeve and Valves and other miscellaneous
<br /> appurtenances : Measurement shall be on the basis of furnishing and installing each
<br /> type and size of appurtenance required, including valve boxes , covers , and other
<br /> associated items . (Except when included in lump sum bid items — eg; aerial crossing,
<br /> directional bore . )
<br /> E . Fire Hydrant Assembly : Measurement of fire hydrant assembly shall be for the
<br /> actual number constructed in accordance with the Plans and Specifications , or as
<br /> directed by the Engineer, at the unit price bid for the item " Fire Hydrant Assembly , "
<br /> scheduled in the Form of Proposal . The unit price for "Fire Hydrant Assembly " shall
<br /> include cutting bituminous paving, removal of paving courses and curb if required,
<br /> excavation , furnishing and installation required length of 6" DIP water main , dry -
<br /> barrel traffic hydrant, concrete foundations for hydrant, fitting, one ( 1 ) 6 " diameter
<br /> gate valve , concrete thrust block (reaction backing) for fire hydrant , backfill , blue
<br /> reflective markers, all materials , equipment, labor and all else necessary therefore
<br /> and incidential thereto .
<br /> F . HDPE Horizontal Directional Bore : Measurement of HDPE horizontal directional
<br /> bore shall be computed using linear feet, as measured prior to pulling, and deducting
<br /> the length of pipe above ground service and include all material ( including HDPE
<br /> pipe), equipment, supplies , fuel , labor, sheeting and bracing, receiving and boring
<br /> pits ( if required) , excavation , dewatering, backfilling , compaction , mechanical
<br /> fittings , restoration , furnishing and in stallion of the HDPE pipe . Payments shall be
<br /> based on a linear foot price for the directional bore length as measured as specified
<br /> above .