D. Engineer will sign and date the Change Order to establish the change in Contract <br />Sum and in Contract Time. <br />E. Owner and Contractor will sign and date the Change Order to indicate their <br />agreement therein. <br />1.11 CORRELATION WITH CONTRACTOR'S SUBMITTALS <br />A. Contractor shall periodically revise Schedule of Values and Request for Payment <br />forms to record each change as a separate item of Work, and to record the <br />adjusted Contract Sum, <br />B. Contractor shall periodically revise the Construction Schedule to reflect each <br />change in Contract Time. <br />i Revise sub -schedules to show changes for other items of work affected <br />by the changes. <br />C. Upon completion of work under a Change Order, enter pertinent changes in <br />Record Documents. <br />PART 2 -- PRODUCTS <br />Not Applicable <br />PART 3 -- EXECUTION <br />Not Applicable <br />** END OF SECTION ** <br />01153-5 <br />