Laserfiche WebLink
3. Show projected percentage of completion for each item. as of the first day of <br />each month. <br />4. Show projected dollar cash flow requirements for each month of construction. <br />1.05 PROGRESS REVISIONS <br />A. Indicate progress of each activity to date of submission <br />B Show changes occurring since previous submission of Schedule <br />1. Major changes in scope. <br />2. Activities modified since previous submission. <br />3. Revised projections of progress and completion. <br />4. Other identifiable changes. <br />C. Provide a narrative report as needed to define: <br />1. Problem areas, anticipated delays, and the impact on the schedule. <br />2. Corrective action recommended, and its effect. <br />3. The effect of changes on schedules of other prime Contractors. <br />1.06 SUBMISSIONS <br />A. Submit initial schedules within ten (10) days after award of Contract: Engineer will <br />review schedules for information only. <br />B. Submit revised progress schedules with each application for payment or monthly, <br />whichever is the shortest period. <br />C. Submit the number of opaque reproductions which the Contractor requires, plus <br />five (5) additional copies; one for Owner and one for Engineer. <br />1.07 DISTRIBUTION <br />A Distribute copies of approved schedules to - <br />1 . <br />o-1. Engineer <br />2. Job site file <br />3. Subcontractors <br />4. Other concerned parties <br />5. Owner (two copies) <br />B. instruct recipients to report promptly to the Contractor, in writing, any problems <br />anticipated by the projections shown in the schedule. <br />PART 2 — PRODUCTS <br />NOT APPLICABLE <br />PART 3 — EXECUTION <br />3.01 RESPONSIBILITY FOR SCHEDULE COMPLIANCE <br />A. The Contractor agrees that whenever it becomes apparent from the current <br />monthly schedule that delays to the critical path have resulted, and hence, that the <br />contract completion date will not be met or when so directed by the Engineer, he <br />01311-2 <br />D1DIVISION 1101311 Construction Schedules.doc <br />