INDIAN RIVER COUNTY JULY 25, 2014 <br />INTERGENERATIONAL RECREATION CENTER 100% CONSTRUCTION DOCUMENTS <br />C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. <br />Time for review shall commence on Architect's receipt of submittal. No extension of the <br />Contract Time will be authorized because of failure to transmit submittals enough in advance of <br />the Work to permit processing, including resubmittals. <br />1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time <br />if coordination with subsequent submittals is required. The Architect will advise <br />Contractor when a submittal being processed must be delayed for coordination. <br />2. Intermediate Review: If intermediate submittal is necessary, process it in same manner <br />as initial submittal. <br />3. Resubmittal Review: Allow 15 days for review of each resubmittal. <br />4. Sequential Review: Where sequential review of submittals by Architect's consultants, <br />Owner, or other parties is indicated, allow 21 days for initial review of each submittal. <br />5. Concurrent Consultant Review: Where the Contract Documents indicate that submittals <br />may be transmitted simultaneously to Architect and to Architect's consultants, allow 15 <br />days for review of each submittal. Submittal will be returned to Architect before being <br />returned to Contractor. <br />D. Paper Submittals: Place a permanent label or title block on each submittal item for <br />identification. <br />1. Indicate name of firm or entity that prepared each submittal on label or title block. <br />2. Provide a space approximately 6 by 8 inches (150 by 200 mm) on label or beside title <br />block to record Contractor's review and approval markings and action taken by Architect. <br />3. Include the following information for processing and recording action taken: <br />a. Project name. <br />b. Date. <br />c. Name of Architect. <br />d. Name of Construction Manager. <br />e. Name of Contractor. <br />f. Name of subcontractor. <br />g. Name of supplier. <br />h. Name of manufacturer. <br />Submittal number or other unique identifier, including revision identifier. <br />1) Submittal number shall use Specification Section number followed by a <br />decimal point and then a sequential number (e.g., 06100.01). Resubmittals <br />shall include an alphabetic suffix after another decimal point (e.g., <br />06100.01.A). <br />j. Number and title of appropriate Specification Section. <br />k. Drawing number and detail references, as appropriate. <br />1. Location(s) where product is to be installed, as appropriate. <br />m. Other necessary identification. <br />4. Additional Paper Copies: Unless additional copies are required for final submittal, and <br />unless Architect observes noncompliance with provisions in the Contract Documents, <br />initial submittal may serve as final submittal. <br />SUBMITTAL PROCEDURES 01 33 00 - 3 <br />