Contract Documents unless CONTRACTOR knew or ate will be held to review for acceptability to ENG1- <br /> reasonably should have known thereof. NEER as provided below the schedules submitted in <br /> accordance with paragraph 2.05.13. CONTRACTOR <br /> B. Preliminary Schedules: Within ten days after shall have an additional ten days to make corrections <br /> the Effective Date of the Agreement(unless otherwise and adjustments and to complete and resubmit the <br /> specified in the General Requirements), CONTRAC•- schedules. No progress payment shall be made to <br /> TOR shall submit to ENGINEER for its timely review: CONTRACTOR until acceptable schedules are <br /> submitted to ENGINEER. <br /> 1. a preliminary progress schedule <br /> indicating the times (numbers of days or dates) 1. The progress schedule will be <br /> for starting and completing the various stages acceptable to ENGINEER if it provides an <br /> of the Work, including any Milestones specified orderly progression of the Work to completion <br /> in the Contract Documents; within any specified Milestones and the <br /> Contract Times. Such acceptance will not <br /> 2. a preliminary schedule of Shop impose on ENGINEER responsibility for the <br /> Drawing and Sample submittals which will list progress schedule, for sequencing, scheduling, <br /> each required submittal and the times for sub- or progress of the Work nor interfere with or <br /> mitting, reviewing, and processing such relieve CONTRACTOR from CONTRACTOR's <br /> submittal; and full responsibility therefor. <br /> 3, a preliminary schedule of values for 2. CONTRACTOR's schedule of Shop <br /> all of the Work which includes quantities and Drawing and Sample submittals will be <br /> prices of items which when added together acceptable to ENGINEER if it provides a <br /> equal the Contract Price and subdivides the workable arrangement for reviewing and <br /> Work into component parts in sufficient detail to processing the required submittals. <br /> serve as the basis for progress payments <br /> during performance of the Work. Such prices 3. CONTRACTOR's schedule of values <br /> will include an appropriate amount of overhead will be acceptable to ENGINEER as to form <br /> and profit applicable to each item of Work. and substance if it provides a reasonable <br /> allocation of the Contract Price to component <br /> parts of the Work. <br /> the Site is started, CONTRACTOR and OWNS all <br /> each deliver to the other, with copi o each ARTICLE 3 -CONTRACT DOCUMENTS: INTENT, <br /> additional insured identified in t upplementary AMENDING, REUSE <br /> Conditions, certificates of urance (and other <br /> evidence of insurance ich either of them or any <br /> additional insur may reasonably request) which 3,01 Intent <br /> CONTRA and OWNER respectively are <br /> A. The Contract Documents are comple- <br /> mentary; what is called for by one is as binding as if <br /> called for by all. <br /> 2.06 Preconstruction Conference <br /> B. It is the intent of the Contract Documents to <br /> describe a functionally complete Project(or part there- <br /> to run, but before any Work at the Site i ;i-a:���ed, a of} to be constructed in accordance with the Contract <br /> conference attended by CONTRACT , ENGINEER, Documents, Any labor, documentation, services, <br /> and others as appropriate wil held to establish a materials, or equipment that may reasonably be <br /> working inferred from the Contract Documents or from <br /> Work and to disc a schedules referred to in para- prevailing custom or trade usage as being required to <br /> graph 2.05. roceduresinrl for handling Shop Drawings produce the intended result will be provided whether <br /> +n in <br /> and er submittals, processing Applications for or not specifically called for at no additional cost to <br /> nf4OWNER. <br /> 2.07 Initial Acceptance of Schedules C. Clarifications and interpretations of the <br /> Contract Documents shall be issued by ENGINEER <br /> A. Unless otherwise provided in the Contract as provided in Article 9. <br /> Documents, at least ten days before submission of the <br /> first Application for Payment a conference attended by <br /> CONTRACTOR, ENGINEER, and others as appropri- <br /> 00700-General Conditions REV 04-07.doc <br /> 00700-9 <br /> F:1Public Works\E N G I N E E R I N G DIVISION PROJECTS11210-Sandridge Driving Range Tee Renovation\Admimlbid documents100700-General Conditions REV 04-07.doc <br /> SmeadSoft Reprint Date:Monday,January 11,2016-09:22:04-OfficialDocuments:9069,Attachment Id 1,Page 76 <br />