Laserfiche WebLink
Proposal for Materials Testing Services Page 2 <br /> Old Dixie Highway Resurfacing ■ Indian River County, Florida <br /> March 2, 2016 ■ Terracon Proposal No. PHB161007 <br /> B. SCOPE OF SERVICES <br /> Based on our understanding of the project schedule and review of the project plans and <br /> specifications, we envision that our field sampling/testing services will be required on a <br /> periodic or as needed basis over the duration of the project. More specifically, our work <br /> will involve the following. <br /> Earthwork— Embankment and LBR 40 Shoulder Stabilization <br /> • Laboratory Proctors (AASHTO T-99 and T-180) to determine maximum density <br /> of the soils used for embankment and pipe backfill. <br /> • In-place density tests of embankment at a frequency of 1 test per 500 If. <br /> • In-place density tests of pipe backfill at a frequency of one test per 500 If (or <br /> fraction thereof) for each lift of backfill placed. <br /> • Limerock Bearing Ratio (LBR) tests of the in-place LBR materials for the <br /> Stabilized Shoulders at a frequency of 1 test about every 2000 linear feet or 5 <br /> LBR samples on each side of roadway (total of 10 tests). <br /> • Thickness verification of completed 12" LBR Shoulder Stabilization. <br /> • In-place density tests of the LBR Shoulder Stabilization at a frequency of 1 test <br /> per 500 linear feet each side of roadway (total of 42 tests). <br /> FDR Base Course <br /> • FDR mix design — Review and evaluate the mix design developed by the <br /> Contractor for its design approach and procedure. <br /> • Full Sieve Analysis test on the virgin materials before injection of emulsion at a <br /> frequency of 1 test every 1000 linear feet per lane (estimated total of 22 tests). <br /> • Maximum Density (Proctor) tests of the in-place FDR base materials at a <br /> frequency of 1 test every 1000 linear feet per lane (estimated total of 22 tests) <br /> • In-place density tests at a frequency of 1 test per 500 linear feet per lane <br /> (estimated total of 42 tests). <br /> • While on-site the technician will communicate with designated County and <br /> Contractor personnel so that items of concern or identified deficiencies can be <br /> immediately corrected. <br /> • Verification of completed FDR base course — Review and evaluate the <br /> verification testing plan as well as the testing results as provided by the <br /> Contractor. <br /> • As a contingency, we have listed our laboratory testing rates for FDR Mix Design <br /> Verification and Resilient Modulus testing in case the contractor's QC laboratory <br /> cannot provide these services. <br /> 1 rerralc®n <br />