However, if Contractor claims entitlement to additional time or money as a result of the Field Order, such <br />entitlement is conditioned upon obtaining a Change Order authorized and executed by Owner after timely <br />making a Claim as provided in the Contract Documents. <br />SC 9.08-A. Delete the second sentence of 9.08A of the General Conditions in its entirety and replace with the <br />following: <br />Except for: (a) Claims for differing subsurface or physical conditions governed by paragraph 4.03; and (b) claims <br />for time extensions governed by paragraph 12.03, all matters in question and other matters between Owner and <br />Contractor arising prior to the date final payment is due, relating to the acceptability of the Work and the <br />interpretation of the requirements of the contract documents pertaining to the performance of the Work, will be <br />referred initially to Engineer in writing within 15 days after occurrence of the event giving rise to such Claim or <br />within 15 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later; <br />provided, however, the Owner shall make all final determination of such matters. <br />SC 9.08-C. Delete paragraph 9.08-C of the General Conditions in its entirety <br />SC 9.08-D. Delete paragraph 9.08-1) of the General Conditions in its entirety <br />SC 10.03 A.3 Delete subparagraph 10.03.A.3 of the General Conditions in its entirety <br />SC 10.05.A. Delete paragraph 10.05.A of the General Conditions in its entirety and replace with the following: <br />A. All Claims shall initially be referred to the Engineer for decision. <br />SC 10.05.13. Delete paragraph 10.05.13 of the General Conditions in its entirety and replace with the following: <br />Except for: (a) Claims for differing subsurface or physical conditions governed by paragraph 4.03; and (b) claims <br />for time extensions governed by paragraph 12.03, Claims by either party shall be initiated within 15 days after <br />occurrence of the event giving rise to such Claim or within 15 days after the claimant first recognizes the <br />condition giving rise to the Claim, whichever is later, by written notice of the amount or extent of the Claim, <br />dispute, or other matter with supporting data to the Engineer and the other party by written notice stating the <br />general nature of each Claim, dispute, or other matter delivered by the claimant to Engineer and the other party to <br />the Contract. A Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of <br />paragraph 12.01.B. A Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions <br />of paragraph 12.02.13. No claim by the Contractor for an equitable adjustment hereunder shall be allowed if asserted <br />after final payment under this Contract. <br />SC 10.05 C, D, and E. Delete paragraphs 10.05C, D, and E. of the General Conditions in their entirety. <br />ARTICLE 11 - COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK <br />SC -11.02A. Delete paragraph 11.02.A of the General Conditions in its entirety and replace with the following: <br />It is understood that CONTRACTOR has included in the Contract Price all allowances so named in the Contract <br />Documents and shall cause the Work so covered to be performed for such sums as may be acceptable to <br />L) OWNER. <br />Delete paragraphs 11.0213 through D of the General Conditions in their entirety. <br />