Page Two <br />Agenda Item for July 16, 2013 <br />Crime Scene Facility Change Order # 3 Proctor Construction Company <br />(W Evidence Compound <br />Item #6- Condenser slabs — (ADD $5,460.00) - This change provides equipment concrete <br />slabs and reinforcing walls to relocate HVAC condensing units. The slabs are directly adjacent <br />to storm water retention areas. The relocation reduces the distance of the refrigerant piping and <br />electrical. <br />Item #7- Air compressor piping — (ADD $2,244.00) - This change provides for material and <br />installation of compressed air from the compressor location to the evidence fume hood located <br />in the evidence processing lab. <br />Item #8 — Additional condensate piping — (ADD $1,045.00) - This change is related to the <br />additional HVAC equipment required for the vehicle processing area and included installation of <br />a drywell as required by code. <br />Item #9- Security System — (ADD $7,170.00) - This change is to provide a partitioned <br />electronic security system to the building to comply with the Security policies of the Sheriffs <br />office. <br />Item #10- Additional framing — (ADD $1,630.00) - This change is to provide additional interior <br />framing for the relocation of exhaust and intake louvers due to modifications to add HVAC in <br />vehicle processing area. <br />Item #11- Change Plywood rating — (ADD $490.00) — This change is to replace existing <br />plywood decking and add inner wall backing for mounted electronic equipment with fire <br />(W retardant materials. <br />Item #12 — Add two benches — (ADD $300.00)- This change adds two benches in the shower <br />area of the restrooms to comply with ADA related building codes. <br />Item #13- Added electrical/Data — (ADD $2,830.00) — This change adds electrical and data <br />outlet locations in areas of the building as per Sheriff Staff walk through. <br />Item #14 — Added electrical AHU-10 — (ADD $849.39)- This change provides electrical service <br />to the HVAC equipment added to the Vehicle processing area. <br />Item #15 — Added galvanized panels — (ADD $1,078.00)- This change increases the quantity <br />of galvanized security mesh panels. <br />Item #16- Added electrical — (ADD $276.65) — This change adds electrical outlets in the photo <br />lab and includes a credit for shortening of other equipment circuits. <br />Item #17 — Added electrical — (ADD $225.57) — This change extends the electrical service to <br />AHU-1 which was relocated to avoid required access to evidence storage vault. <br />Item #18 — Sewer line — (ADD $2,423.00) - The sewer line replacement authorized in COM <br />was revised to lower the invert of the line. This requires a deeper trench and will require a gravel <br />bed in the trench. <br />Item #19- Owner contingency CREDIT — (DEDUCT $7,212.30) - This is the credit towards <br />charges listed above and reduces the owner contingency amount to Zero Dollars. <br />Misc — (ADD $11,043.98) 10% Overhead markup, 5% ,Profit markup, 1% Insurance markup,1% <br />(W Bond markup. <br />F:\PublicWorks\Luanne M\Facilities Management\Sheriff Storage -New Bldg & Future Facility\Change order#3 2 <br />Proctor Construction crime scene 07-09-13.doc 97 <br />