SECTION 01770 <br /> CLOSEOUT PROCEDURES <br /> B. Inspection: Submit a written request for inspection for Substantial Completion. On <br /> receipt of request,Architect will either proceed with inspection or notify Contractor <br /> of unfulfilled requirements. Architect will prepare the Certificate of Substantial <br /> Completion after inspection or will notify Contractor of items,either on Contractor's <br /> list or additional items identified by Architect, that must be completed or corrected <br /> before certificate will be issued. <br /> 1. Reinspection: Request reinspection when the Work identified in previous <br /> inspections as incomplete is completed or corrected. <br /> 2. Results of completed inspection will form the basis of requirements for Final <br /> Completion. <br /> 1.4 FINAL COMPLETION <br /> A. Preliminary Procedures: Before requesting final inspection for determining date of <br /> Final Completion, complete the following: <br /> 1. Submit a final Application for Payment according to Division 1 Section <br /> "Payment Procedures." <br /> 2. Submit certified copy of Architect's Substantial Completion inspection list of <br /> items to be completed or corrected (punch list), endorsed and dated by <br /> Architect. The certified copy of the list shall,state that each item has been <br /> completed or otherwise resolved for acceptance. <br /> 3. Submit evidence of final, continuing insurance coverage complying with <br /> insurance requirements. <br /> 4. Submit pest-control final inspection report and warranty. <br /> 5. Instruct Owner's personnel in operation, adjustment, and maintenance of <br /> products, equipment, and systems. Submit demonstration and training <br /> videotapes. <br /> B. Inspection: Submit a written request for final inspection for acceptance. On <br /> receipt of request,Architect will either proceed with inspection or notify Contractor <br /> of unfulfilled requirements. Architect will prepare a final Certificate for Payment <br /> after inspection or will notify Contractor of construction that must be completed or <br /> corrected before certificate will be issued. <br /> 1. Reinspection: Request reinspection when the Work identified in previous <br /> inspections as incomplete is completed or corrected. <br /> 1.5 LIST OF INCOMPLETE ITEMS (PUNCH LIST) <br /> A. Preparation: Submit three copies of list. Include name and identification of each <br /> space and area affected by construction operations for incomplete items and items <br /> needing correction including, if necessary, areas disturbed by Contractor that are <br /> outside the limits of construction. <br /> 01770 Closeout Procedures <br /> 01770-2 <br /> F:\Public Works\ENGINEERING DIVISION PROJECTS\1765 Sebastian Corners Roof Replacement\1-Admin\Bid Documents\Master Contract <br /> Documents\Master Contract Documents\01770-Closeout Procedures.doc <br />