punch list within this period, the Owner will have the right to impose liquidated <br /> damages in the amount of one thousand two hundred forty one ($1,241.00) dol- <br /> lars for each consecutive day until all of the items are completed. <br /> 1.04 FINAL COMPLETION <br /> A. Preliminary Procedures: Before requesting final inspection for determining date of Final <br /> Completion,complete the following: <br /> 1. Submit signed copy of Engineer's inspection list of items to be completed or cor- <br /> rected (punch list). The certified copy of the list shall state that each item has <br /> been completed or otherwise resolved for acceptance. <br /> 2. Submit evidence of fastener pull tests to building department for archival. <br /> 3. Submit evidence of final, continuing insurance coverage complying with insur- <br /> ance requirements. <br /> 4. Instruct Owner's personnel in operation, adjustment, and maintenance of prod- <br /> ucts,equipment,and systems. <br /> B. Final Inspection: The submission of the signed punch list constitutes as written request <br /> for final inspection for acceptance. On receipt of request, Engineer along with the Own- <br /> er's Representative will conduct a final inspection within seven(7)days of receipt of cer- <br /> tification. <br /> 1. Should the Engineer consider that the Work is finally complete in accordance <br /> with requirements of the Contract Documents, he will request the Contractor to <br /> make Project Closeout Submittals. <br /> 2. Should the Engineer consider that the Work is not finally complete,he will notify <br /> the Contractor, in writing,stating the reasons. <br /> 3. The Contractor shall take immediate steps to remedy the stated deficiencies, and <br /> send a second written notice to the Engineer certifying that the Work is complete, <br /> at which time the Engineer will re-inspect the Work. <br /> 1.05 PROJECT RECORD DOCUMENTS <br /> A. General: Do not use Project Record Documents for construction purposes. Protect Pro- <br /> ject Record Documents from deterioration and loss. Provide access to Project Record <br /> Documents for Engineer's reference during normal working hours. <br /> 1. The Contractor shall submit all required record documents and warranties within <br /> thirty (30) days of the punch list inspection. If the Contractor fails to properly <br /> submit all required items within this period, the Owner will have the right to im- <br /> pose liquidated damages in the amount of one thousand two hundred forty one <br /> ($1,241.00) dollars for each consecutive day until all of the items are properly <br /> submitted. <br /> B. Record Drawings: Maintain and submit one set of blue- or black-line white prints of <br /> Contract Drawings and Shop Drawings. <br /> 1. Mark Record Prints to show the actual installation where installation varies from <br /> that shown originally. Require individual or entity who obtained record data, <br /> whether individual or entity is Installer, subcontractor, or similar entity, to pre- <br /> pare the marked-up Record Prints. <br /> a. Give particular attention to information on concealed elements that can- <br /> Sebastian Corners Roof Replacement 01 77 00-2 Closeout Procedures <br />