Jones Pier Conservation Area <br />Manhour Breakdown <br />2/7/2020 <br />TASK HOURS <br />I) Administrative Tasks Principal Engineer I Inspector <br />1 Pre Construction Meeting 2 2 <br />2 Weekly Progress Meetings (1 Weekly / 6 Mo. Duration - 26 Meetings) 13 13 <br />3 Review Contractor's Schedule Updates 16 <br />4 Coordination with Outside Design Consultants 8 <br />5 Respond to Contractor RFI's and provide Clarifications 2 8 <br />6 Shop Drawing Review 2 8 <br />7 Geotechnical Report Review 4 <br />8 Consultation with IRC and Processing Change Order Requests as Necessary 4 4 <br />9 Review Pay Requests and Submit to IRC once approved. 12 <br />Total Hours 63 35 0 <br />Hourly Rate $165/HR $140/HR $65/HR <br />Total Cost $10,395 $4,900 $0 $15,295 <br />II) Site Inspections Principal Engineer 1 Inspector <br />10 Silt Fencing Inspection 4 <br />11 MOT Plan Inspection During Jungle Trail Closing 4 <br />12 Construction Oversight - Average of 3 site inspections / Week 156 <br />13 Pump Material and !installation Inspections. 4 <br />14 Pump Electrical Controls Installations 4 <br />15 Pipe Material and Installation Inspections 4 <br />16 Water Connection and Pressure Test Observations 1 2 <br />17 Sewer Connection and Testing Observations 1 2 <br />Total Hours 0 14 168 <br />Hourly Rate $165/HR $140/HR $65/HR <br />Total Cost $0 $1,960 $10,920 $12,880 <br />III) Project Closeout Principal Engineer 1 Inspector <br />18 Conduct Final Inspections and Prepare Punch -List 4 4 <br />19 Review of As -built Survey for Compliance with Plans 2 2 <br />20 Review Phase 1 Final Certification to IRC 1 <br />21 Review Phase 1 Final Certification to SJRWMD 1 <br />Total Hours 8 6 0 <br />Hourly Rate. $165/HR $140/HR $65/HR <br />Total Cost $1,320 $840 $0 $2,160 <br />$30,335 <br />31 <br />