IRC -1505 <br />SC -6.06 Concerning Subcontractors, Suppliers, and Others <br />SC -6.06.C. Add the following sentence at the end of paragraph GC-6.06.C.- <br />OWNER <br />C-6.06.C. <br />OWNER or ENGINEER may furnish to any such Subcontractor, Supplier, or other individual or entity, to <br />the extent practicable, information about amounts paid to CONTRACTOR on account of Work performed <br />for CONTRACTOR by a particular Subcontractor, Supplier, or other individual or entity. <br />SC -6.08 Permits <br />SC -6.08 Add the following paragraphs immediately after paragraph GC -6.08.A: <br />The OWNER has obtained the following permits (copies of these permits are contained in <br />Appendix A): <br />A. St. Johns River Water Management District - Permit No. 87006-13, dated <br />11/17/2020 <br />B. St. Johns River Water Management District - Permit No. 69244-6, dated <br />12/15/2020 <br />C. Indian River Farms Water Control District - Permit No. 18-03, dated 08/01/2017 <br />D. Department of the Army - Permit No. SAJ-2017-01526 (NW -JCL), dated <br />07/17/2017 <br />2. The CONTRACTOR shall obtain and pay for all other required permits and <br />licenses. The CONTRACTOR shall provide copies of the permits to the <br />OWNER and ENGINEER and shall comply with all conditions contained in <br />the permits at no extra cost to the OWNER. <br />3. The CONTRACTOR shall be familiar with all permit requirements during <br />construction and shall be responsible for complying with these <br />requirements. The cost of this effort shall be included in the pay item in <br />which the work is most closely associated with. <br />SC -9.05 Authorized Variations in Work <br />SC -9.05.A. Delete the second sentence in paragraph GC -9.05.A in its entirety. <br />SC -11.01 Cost of the Work <br />SC -11.01.A.1. Delete paragraph GC -11.01.A.1 in its entirety, and insert the following sentences in its place: <br />1. CONTRACTOR will receive payment for actual costs of direct labor and burden (see SC - <br />2.06.6) for the additional or unforeseen work. Labor includes foremen actually engaged in <br />the work; and will not include project supervisory personnel nor necessary on-site clerical <br />staff, except when the additional or unforeseen work is a controlling work item and the <br />performance of such controlling work item actually extends completion of the project due <br />to no fault of the Contractor. Compensation for project supervisory personnel, but in no <br />case higher than a Project Manager's position, shall only be for the pro -rata time such <br />supervisory personnel spent on the contract. In no case shall an officer or director of the <br />Company, nor those persons who own more than 1% of the Company, be considered as <br />project supervisory personnel, direct labor or foremen hereunder. The expenses of <br />performing Work outside of regular working hours, on Saturday, Sunday, or legal holidays, <br />shall be included in the above to the extent authorized by OWNER. <br />Supplementary Conditions - 00800-8 <br />FAPublic Works\ENGINEERING DIVISION PROJECTS\1505-66th Ave Widening_49th St to 69th St\1-Admin\Bid Documents\Master Contract Documents\DIV 0 5 Conditions <br />of the Contract.docx <br />