OHL USA, Inc. - Projects Completed Within Last Five Years
<br />Project Name
<br />Contract Value
<br />Project Owner and Contact
<br />Description
<br />Completion Date
<br />HCTRA Hardy Toll Road Maintenance
<br />TxDOT
<br />Construction involved drainage and bridge
<br />C421
<br />$ 24,114,811.20
<br />Matt Kainer
<br />maintenance work including the widening of the
<br />April 1, 2018
<br />Houston, Texas
<br />713-587-7835
<br />tollway.
<br />Williamson County FM 1460
<br />TxDOT - Texas Department of-ranspotation
<br />Replacement of 3.68 miles of 2 lane Farm to Market
<br />$ 22,042,000.04
<br />Jasor Hudson
<br />Rd with 4 Lane divided Roadway; two new bridges
<br />December 5, 2018
<br />Williamson County, TX
<br />512-930-6012
<br />and major drainage upgrades.
<br />NASA - Building 21
<br />NASA-USACE
<br />OHL scope involves demolition, clearing and
<br />$ 58,800,000.00
<br />Jeff Balthrop (Prime Con:act)
<br />grubbing, earthwork and site utilities relocation and
<br />Nov -17
<br />Houston, TX
<br />832-777-7545
<br />installation.
<br />IH -35E Widening -South Section;
<br />TxDOT
<br />Widening of outside main lane NBML & SBML
<br />$ 36,459,000.09
<br />Michelle Releford
<br />approx 19 miles along IH 35E from South to the Hill
<br />May 24, 2018
<br />Waxahachie, TX
<br />214-320-4485
<br />County Line
<br />TxDOT
<br />Rehab bridge approach concrete pavement at 5 EB
<br />SH225, Hams County, TX
<br />$ 2,834,757.26
<br />Melody Galland
<br />and WB from BW 8 to Tidal Rd 3.2 miles Proj ID:
<br />Apr -18
<br />281-464-5510
<br />NH 2016(060); CSJ: 0502-01-210 CSJ 0502-01-210
<br />Widening of IH 35 thru Austin from William Cannon
<br />Travis - IH 35 Widening at Wm Cannon
<br />TxDOT - Texas Department of Transportation
<br />Dr to Stassney Lane. Removal and replacement of
<br />Drive
<br />$ 86,046,258.82
<br />Mike Miller
<br />the Stassney Lane & William Cannon Overpasses
<br />January 9, 2020
<br />Austin, TX
<br />512-585-3318
<br />and the addition of tum -around bridges to both
<br />locations.
<br />Travis - IH 35 (East Oltorf)
<br />$ 47,832,900.29
<br />TxDOT
<br />Mike McKissick
<br />Added shoulders, auxilary lanes, ramp
<br />July 15, 2020
<br />Austin, TX
<br />512-997-2200
<br />improvements, pavement
<br />Denton - IH 35
<br />$ 29,900,178.21
<br />TxDOT
<br />Jay Loomis
<br />Grade seperation along IH 35E at Brinker and State
<br />August 13, 2020
<br />Denton County, TX
<br />940-323-1835
<br />School Rd/Mayhill Rd
<br />SH 130 North - Widening from SH 45
<br />$ 40,670,004.76
<br />TxDOT
<br />Kyle Russell, PM
<br />Widening 9 miles to add a third lane on SH 130 in
<br />October 13, 2020
<br />North to US 290 East; Travis County, TX
<br />737-215-7485
<br />both directions, widen the main lanes and bridges.
<br />SR826 (Palmetto Expressway) / SR836
<br />FDOT-D6
<br />reconstruction and widening of an interchange,
<br />(Dolphin Expressway) Interchange
<br />$ 567,490,000.00
<br />Andres Berisiartu, PE C.G.C.
<br />including 46 new bridges, widening of existing SR-
<br />February 19, 2017
<br />Reconstruction
<br />305-640-7412
<br />836. Total corridor improvements 16 miles.
<br />Miami -Dade County, FL
<br />Completed Projects Page 3