Laura Yonkers, PE, CFM <br />February 14, 2023 <br />Page 4 <br />Task 2 will consist of three submittals - Basis of Design TM, 75%, and Final Design <br />deliverables. The CONSULTANT will participate in a review meeting scheduled during Task 2 <br />at the County's discretion to discuss and obtain comments from COUNTY following <br />Submittals. Changes agreed to will be incorporated into the Final Design Submittal <br />documents. <br />BASIS OF DESIGN TM <br />The TM will be submitted to County for review and comment and will include the following: <br />■ Summary of relevant existing conditions. <br />■ Assumptions. <br />■ Hydraulic calculations for the new headworks. <br />■ Conceptual sketches of new aboveground headworks alternatives that provide even flow <br />distribution across the ATS with fewer valves, simpler operation, and less maintenance. <br />■ Sketches supporting ATS concrete slab repair and joint sealing. <br />■ Engineer's Opinion of Probable Construction Cost. <br />COUNTY Responsibility: <br />■ Review and provide feedback on the Basis of Design TM. <br />■ Possible meeting with the CONSULTANT to review the Basis of Design TM. <br />Deliverables: <br />■ One electronic copy (.pdf) of the Draft and Final Basis of Design TM. <br />Key Assumptions: <br />■ The COUNTY will require a 2 -week minimum review time of the submittal. <br />75% DESIGN SUBMITTAL <br />The 75% Design Submittal Package will be submitted to the COUNTY for review and <br />comment and will include the following: <br />■ Design Drawings - Draft versions of the sheets listed in the table above. <br />■ Technical Specifications - A Table of Contents will be included in the 75% design. <br />■ Engineer's Opinion of Probable Construction Cost. <br />COUNTY Responsibility: <br />• Review and provide feedback on the 75% Submittal. <br />■ Possible meeting with the CONSULTANT to review the 75% Submittal. <br />