Laserfiche WebLink
• <br />40 <br />i <br />SECTION 01025 <br />MEASUREMENT AND PAYMENT <br />PART I -- GENERAL <br />1.01 GENERAL <br />Measurement and payment will be based upon work completed and accepted in <br />accordance with the Contract Documents. No separate payment will be made for <br />excavation, trenching dewatering, backfilling, leakage tests, surveying, density tests, <br />or other incidental items of work not shown in the Agreement. <br />9.02. EQUIPMENT AND MATERIALS IN STORAGE <br />Partial payment for materials and equipment in proper storage at the site of die work <br />or other approved storage site will be made for those items For wbich the Contractor <br />has submitted paid invoices to the Engineer. The partial payment for stored materials <br />will be 50% of the value of materials and equipment, based on reccipted bills, <br />furnished but not tncorpor-atcd in file ►work, as determined by Engineer. <br />1.03 MEASUREMENT <br />A. Mobilization: Measurement shall be on a lump sum basis, and shall be limited to the <br />following maximum amounts: <br />ORIGINAL CONTRACT AMOUNT ($) <br />NIAXIMUM AMOUNT OF <br />FROM MORE THAN <br />TO AND INCLUDING <br />ITEM FOR MOEILIZAT70N <br />0 <br />100,000 <br />3,000 <br />100,000 <br />500,000 <br />15,000 <br />500,000 <br />1,000,000 <br />30,000 <br />1,000,000 <br />2,000,000 <br />60,000 <br />2,000,000 <br />3,000,000 <br />90,000 <br />3,000,000 <br />4,000,000 <br />120,000 <br />4,000,000 <br />5,000,000 <br />125,000 <br />5,000,000 <br />6,000,000 <br />150,000 <br />6,000,000 <br />7,000,000 <br />175,000 <br />7,000,000 <br />10,000,000 <br />200,000 <br />10,000,000 <br />------------- <br />250,000 <br />Should the lump sum price bid for the item Mobilization exceed the maximum <br />permissible amount for this item, as specified herein, the bid price will be reduced to <br />tate maximum permissible amount, and the reduced price will be used in correctly <br />determining the total price for comparison of bids received. The cost of video taping <br />the pre -construction condition shall be included in the lump -sum cost of <br />Mobilization. <br />B. Pipe: Pipe will be measured along the centerline of the pipe installed. No deduction <br />will be made for the length of valves and fittings installed in the line. Where: the <br />measurement terminates at a valve, bend, tec, or other fitting, the ccntcrline of the <br />01025»t. <br />