SC -13.03 Test and Inspections <br />SC -13.03.B. Delete paragraph GC -13.03.8 in its entirety, and insert the following sentences in <br />its place: <br />B. OWNER shall employ and pay for the services of an independent testing laboratory to <br />perform all initial inspections, tests, or approvals required by the Contract Documents <br />except those inspections, tests, or approvals listed immediately below. Subsequent <br />inspections, tests, or approvals required after initial failing inspections, tests, or <br />approvals shall be paid for by the CONTRACTOR by back charge to subsequent <br />applications for payment. The CONTRACTOR shall arrange, obtain, and pay for the <br />following inspections, tests, or approvals: <br />1. inspections, tests, or approvals covered by paragraphs 13.03.0 and 13.03.D <br />below; <br />2. costs incurred in connection with tests or inspections conducted pursuant to <br />paragraph 13.04.6 shall be paid as provided in said paragraph 13.04.B; <br />3. tests otherwise specifically provided in the Contract Documents. <br />SC -13.05 OWNER May Stop the Work <br />SC -13.05.A. Delete paragraph GC -13.05.A in its entirety and insert the following paragraph in its <br />place: <br />A. If the Work is defective, or CONTRACTOR fails to supply sufficient skilled <br />workers or suitable materials or equipment, or fails to comply with permit <br />requirements, or fails to comply with the technical specifications, or fails to <br />perform the Work in such a way that the completed Work will conform to the <br />Contract Documents, OWNER may order CONTRACTOR to stop the Work, or any <br />portion thereof, until the cause for such order has been eliminated; however, this <br />right of OWNER to stop the Work shall not give rise to any duty on the part of <br />OWNER to exercise this right for the benefit of CONTRACTOR, any <br />Subcontractor, any Supplier, any other individual or entity, or any surety for, or <br />employee or agent of any of them. <br />SC -13.07 Correction Period <br />SC -13.07 A. Delete the first sentence of paragraph GC -13.07.A in its entirety and insert the <br />following sentence in its place <br />A. If within one year after the date of Final Completion or such longer period of time <br />as may be prescribed by Laws or Regulations or by the terms of any applicable <br />special guarantee required by the Contract Documents or by any specific provision <br />of the Contract Documents, any Work is found to be defective, or if the repair of <br />any damages to the land or areas made available for CONTRACTOR's use by <br />OWNER or permitted by Laws and Regulations as contemplated in paragraph <br />6.11.A is found to be defective, CONTRACTOR shall promptly, without cost to <br />OWNER and in accordance with OWNER's written instructions: (i) repair such <br />defective land or areas, or (ii) correct such defective Work or, if the defective Work <br />has been rejected by OWNER, remove it from the Project and replace it with Work <br />that is not defective, and (iii) satisfactorily correct or repair or remove and replace <br />any damage to other Work, to the work of others or other land or areas resulting <br />therefrom. <br />00800-8 <br />00800 - Supplementary Conditions 05-13 rev <br />00800 8F:\Public Works\ENGINEERING DIVISION PROJECTS\1413-Martin Luther King Walking Trail\Admin\bid documents\Master Contract Documents\00800 - <br />Supplementary Conditions 05-13 rev.doc <br />