' 2 . Trenches shall be made wide enough to allow amini <br /> mum of 2 orches between <br /> parallel pipe lines . The minimum vertical clearance between lines crossing at <br /> ' angles greater than 45 degrees is 1 inch. Trenches for pipe lines shall be made <br /> of sufficient depth to provide the minimum cover from finish grade as follows : <br /> ' a. 16 in. minimum cover over main lines . <br /> b . 16 in, minimum cover over control wires . <br /> c. 12 in . minimum cover over lateral lines to heads . <br /> 3 . Where possible, install pipe adjacent to curbs or paving to minimize <br /> ' interference with plants and their roots. Coordinate with landscape installer <br /> regarding proposed plant material locations . <br /> t4 . Keep trenches free of obstruction and debris that could tend to damage pipe <br /> and control wires. Remove excess soil from the site and leave grade as it was <br /> ' prior to sprinkler system installation. Piping shall be routed around shrubs, <br /> trees and other permanent obstacles . <br /> B . PIPE LINE ASSEMBLY <br /> 1 . Install plastic pipe as recommended by the manufacturer . and provide for <br /> ' expansion and contraction . Cut plastic pipe square. Remove burrs at cut ends <br /> prior to installation so that a smooth unobstructed flow will be obtained . <br /> ' 2 . Install remote control valves at locations no closer than 12 inches to walk <br /> edges, buildings, and walls . Plastic pipe and fittings shall be solvent welded <br /> using solvents and methods as recommended by manufacturer of the pipe, <br /> except where screwed connections are required. Pipe and fittings shall be <br /> ' thoroughly cleaned of dirt, dust and moisture before applying solvent with a <br /> nonsynthetic bristle brush. Care should be taken not to use an excess amount <br /> of solvent, thereby causing a burr or obstruction to form on the inside of the <br /> pipe . Allow the joints to set at least 24 hours before applying pressure on PVC <br /> pipe . Do not use PVC cement which has begun to gel. Do not attempt to <br /> make pipe connections during inclement weather conditions. <br /> C . SPRINKLER HEADS : Large gear-driven rotary type shall be installed so that the <br /> top is slightly above finish grade . If finish grade has not been established, set the <br /> top four inches above grade and lower when finish grade has been achieved . <br /> Sprinklers on risers shall be set at elevations so that there is no interruption of the <br /> stream from the sprinkler nozzle caused by plant material during the first growing <br /> season ( 1 year from date of installation) . Heads along curbs and walks shall be set <br /> flush to within 118 inch and two to four inches away from curb or walk. Adjust <br /> heads having an adjustment stem, for the proper radius and throw for the area <br /> ' involved . <br /> D . CONTROL WIRES : Shall be installed in a neat and orderly fashion underneath <br /> 2B - 5 <br />