C . Testing shall be conducted after backfilling has been completed and <br /> before placement of permanent surface . <br /> D . Testing Procedure shall be as follows : <br /> 1 . Fill line slowly with water. Maintain flow velocity less than two feet <br /> per second . <br /> 2 . Expel air completely from the line during filling and again before <br /> applying test pressure . Air shall be expelled by means of taps at <br /> points of highest elevation . <br /> 3 . Apply initial test pressure and allow to stand without makeup <br /> pressure for two to three hours , to allow for diametric expansion or <br /> pipe stretching to stabilize . <br /> 4 . After this equilibrium period , apply the specified test pressure and <br /> turn the pump off. The final test pressure shall be held for one to <br /> three hours . <br /> 5 . Upon completion of the test, the pressure shall be bled off from a <br /> location other than the point where pressure is monitored . The <br /> pressure drop shall be witnessed by the resident project <br /> representative at the point where the pressure is being monitored <br /> and shall show on the recorded pressure read-out submitted to <br /> the Engineer. <br /> E . Allowable amount of makeup water for expansion during the pressure test <br /> shall conform to Chart 6 , Allowance for Expansion Under Test Pressure , <br /> Technical Report TR 31 /9-79 , published by the Plastic Pipe Institute <br /> ( PPI ). If there are no visual leaks or significant pressure drops during the <br /> ' final test period , the installed pipe passes the test. <br /> F . In any test of pipe laid disclosed leakage significant pressure drip greater <br /> than the allowed , the Contractor shall , at his/her own expense , locate and <br /> repair the cause of leakage and retest the line . The amount of leakage <br /> which will be permitted shall be in accordance with AWWA C600 <br /> Standards . <br /> G . All visible leaks are to be repaired regardless of the amount of leakage . <br /> ' K The Contractor must submit his plan for testing to the Engineer for review <br /> at least ten ( 10 ) days before starting the test. <br /> ' 1 . 10 CLEANING <br /> A . At the conclusion of the work, thoroughly clean all of the new pipelines to <br /> remove all dirt, stones, pieces of wood or other material which may have <br /> entered during the construction period . Debris cleaned from the lines shall <br /> be removed from the job site . If, after this cleaning, any obstructions <br /> remain, they shall be removed. <br /> END OF SECTION <br /> 02627 - 8 <br /> RlUtilities\UTILITY - ENGINEERING\WTP - North RO\N RO Brine Line Discharge - UCP#2208\BID DOCUMENTS North County <br /> RO\BID DOCUMENTS\02627 Water Mains High Density Ployethylene.doc <br />